Question #11 (Topic: Single Topic)
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
A. If more details are needed during Sprint Planning
B. If there is a large number of stories to estimate
C. If there is a small number of stories to estimate
Answer: B
Question #12 (Topic: Single Topic)
What is the objective of the Scrum-of-Scrums meeting?
A. To inform management about the progress of the project.
B. Bring together all team members of all teams.
C. Coordinate the work of multiple Scrum teams.
D. Kick-off an international Scrum project.
Answer: C
Question #13 (Topic: Single Topic)
During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
What is the velocity of the team?
A. 18
B. 24.5
C. 31
Answer: A
Question #14 (Topic: Single Topic)
Which statement describes Release Planning?
A. After looking at all the stories in the backlog, the team estimates their effort in detail.
B. The team meets with the customer to negotiate the scope, cost and time of the release.
C. The team and the Product Owner agree on an initial plan for the delivery of features.
Answer: C
Question #15 (Topic: Single Topic)
Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan.
What term best describes the multi-level planning?
What term best describes the multi-level planning?
A. Planning Onion
B. Planning Poker
C. Sprint Planning
Answer: A