Question #11 (Topic: )
You are a program manager who is using Microsoft PPM and Microsoft Project to manage
an e-commerce portal development program.
The program is separated into individual projects that represent each area of development,
so that each group can manage its own tasks while still having progress visibility at the
program level.
You need to be able to manage the overall program as well as its associated individual
projects within Project Center. This includes the project sites associated with both the
program and the individual projects. Each individual project site should be a subsite of the
overall program project site.
You need to create the master program, the individual projects, and their associated project
sites.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-12_2.png]
an e-commerce portal development program.
The program is separated into individual projects that represent each area of development,
so that each group can manage its own tasks while still having progress visibility at the
program level.
You need to be able to manage the overall program as well as its associated individual
projects within Project Center. This includes the project sites associated with both the
program and the individual projects. Each individual project site should be a subsite of the
overall program project site.
You need to create the master program, the individual projects, and their associated project
sites.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-12_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-12_3.png]
Question #12 (Topic: )
You are a project manager in an organization that is using Microsoft PPM for work
management.
You have already accepted all status updates in the Approval Center, but you are still
unable to see the updates in your project schedule.
You need to ensure that status updates are reflected in your project schedule.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-13_2.png]
management.
You have already accepted all status updates in the Approval Center, but you are still
unable to see the updates in your project schedule.
You need to ensure that status updates are reflected in your project schedule.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-13_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-14_2.png]
Question #13 (Topic: )
You are a team member on a project that uses Microsoft PPM timesheets for work
management. You submit your timesheet by selecting Turn In Final Timesheet.
You observe that some actual work is missing from your timesheet.
You need to be able to enter actual work in your timesheet for the project period.
Which three actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-15_2.png]
management. You submit your timesheet by selecting Turn In Final Timesheet.
You observe that some actual work is missing from your timesheet.
You need to be able to enter actual work in your timesheet for the project period.
Which three actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-15_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-15_3.png]
Question #14 (Topic: )
An organization uses Microsoft PPM to manage content related to projects.
You need to prevent Microsoft PPM from creating a project site when a new project is
created.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-17_2.png]
You need to prevent Microsoft PPM from creating a project site when a new project is
created.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area, and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-17_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-17_3.png]
Question #15 (Topic: )
You are a project manager for an organization that uses Microsoft PPM. You plan each
project in phases.
Team members must only see the assignments from a selected phase. All reports and
project schedule views must reflect the entire project schedule, so the entire project is
visible to the management team.
You need to configure Microsoft PPM.
What should you do?
project in phases.
Team members must only see the assignments from a selected phase. All reports and
project schedule views must reflect the entire project schedule, so the entire project is
visible to the management team.
You need to configure Microsoft PPM.
What should you do?
A. Set the Publish field to No for all tasks that need the assignments to be hidden from the team members.
B. Delete the assignments that are not ready to be published to the team members.
C. Set up a new security category for the management team.
D. Set the booking type to Proposed for all tasks that need the assignments to be hidden from the team members.
Answer: D