Microsoft 70-348 - Managing Projects and Portfolios with Microsoft PPM Exam

Question #6 (Topic: )
You are project manager in your companys PMO. You have permission to manage the
Enterprise Global view in Microsoft PPM. Your organization works with many large
multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your
colleagues to control whether a task is published, who will be responsible for sending the
task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-6_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-7_2.png]
Question #7 (Topic: )
Your organization is in the process of implementing Microsoft PPM.
You need to configure Microsoft PPM to ensure that project managers can choose the
tracking method for each of their projects.
On the Task Settings and Display page, what should you do?
A. Set the tracking method to Free form. B. Select the check box Force project managers to use the progress reporting method specified above for all projects. C. Clear the check box Force project managers to use the progress reporting method specified above for all projects. D. Set the tracking method to Percent of work complete.
Answer: A
Question #8 (Topic: )
You are the project manager for a real estate management company. You are using
Microsoft Project to manage the development of a new restaurant. The schedule includes a
task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment
on June 9, 2016.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate
option from each list in the answer area.
[Microsoft-70-348-8.0/Microsoft-70-348-8_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-9_2.png]
Question #9 (Topic: )
You are the administrator for an organization that uses Microsoft PPM.
Users must be able to create projects by using predefined templates.
You need to create a new Enterprise Project Template and make it available for users.
In which order should you perform the actions? To answer, move all of the actions from the
list of actions to the answer area and arrange them in the correct order.
[Microsoft-70-348-8.0/Microsoft-70-348-10_2.png]
Answer: [Microsoft-70-348-8.0/Microsoft-70-348-10_3.png]
Question #10 (Topic: )
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your companys templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
A. From Microsoft Project, select Enterprise. B. In Project Center, select New, and then select the desired enterprise project type. C. In Resource Center, select New. D. From Microsoft Project, select Featured.
Answer: A,B