Nokia SDM-2002001050 - SDM Certification - NI Exam
Page: 1 / 32
Total 160 questions
Question #1 (Topic: )
During the bidding phase, what type of support can be provided by the PPM (Project
Procurement Manager)?
Procurement Manager)?
A. Ensure cost efficient, qualified and compliant 3rd party solutions for the customer project.
B. None. PPM is responsible for negotiating the 3rd party contracts after the deal with the customer is closed.
C. Prepare training plans to develop 3rd Party competence level.
D. Proactively develop the supply chain for required materials.
Answer: A
Question #2 (Topic: )
Which statement describes BEST the purpose of a project management plan ?
A. The project management plan defines in detail how the project is going to deliver the contracted scope.
B. The project management plan nominates the Project Manager and describes the Scope of Work.
C. The project management plan documents the handover from sales to execution.
D. The project management plan is used to get management approval for project execution.
Answer: A
Question #3 (Topic: )
When can the project management plan be modified?
A. Up to the start of project execution, from then on the project management plan must be frozen as a baseline for future reference.
B. In case the scope of work has changed.
C. Over time during the project as it has at any time to reflect the latest status of the agreed practices, processes and responsibilities.
D. When the PM receives the handover from Sales do Delivery.
Answer: C
Question #4 (Topic: )
When must a Change Management process be initiated?
A. When there is a significant change in the scope of the project.
B. When the Customer sends a formal request for additional Scope of Work.
C. When the CT Head acknowledges that the customer will accept to negotiate the changes in the scope of the contract.
D. Whenever the project execution requires services or materials different from those agreed in the contractual scope of work.
Answer: D
Question #5 (Topic: )
How should integration engineer resources be planned for the RA network integration?
A. Include an estimation of local resources in the project headcount.
B. Prepare an RFQ for external suppliers with the support of Procurement.
C. Include the input from GNIC into your service cost estimation.
D. Communicate the need of integration engineers for your project during the MRM (Monthly Resource Meeting).
Answer: C