What are mandatory steps for Logistics to ship equipment to site?

  • A. Sales Order and Site Material Request issued by the project.
  • B. Site address and Customer approval.
  • C. Civil works completed and TI manager sends delivery request to Logistics.
  • D. Purchase Order to subcontractor and Logistic packing list prepared.


Answer : A

What are the 2 main inputs for the cost baseline calculation?

  • A. Subcontracted Services and Overhead.
  • B. Subcontracted Services and Local Material Purchases.
  • C. Costs of Internal Resources and Costs of Direct External Workforce.
  • D. Resources and Subcontracted Services


Answer : D

DELT-I is a metric that will give visibility of:

  • A. Average lead times of the invoicing process.
  • B. Average Telecom Implementation lead times.
  • C. Timely usage of IPM measuring average delay in key milestones updates.
  • D. Lead times between MS16 Implementation Ends and Internal Acceptance.


Answer : C

Internal acceptance is a milestone that will trigger:

  • A. SAP Billing block released.
  • B. SAP Goods Receipt.
  • C. Customer invoicing.
  • D. Cost Estimation To Completion (ETC).


Answer : B

Demand Planning meetings will generate inputs to:

  • A. SAP, with impacts to sales estimations.
  • B. Rollo, with impacts to volumes estimations.
  • C. MRA, with impact to resource allocations to project team.
  • D. Nelle, with impacts to Supply Chain and PRS(Profitability Reporting System) figures.


Answer : D

What are the two key elements to calculate the Project Cost Adherence (PCA)?

  • A. Cost Overrun of the Period and Total Costs of Sales of the Period.
  • B. Estimate at Completion and Cost Baseline.
  • C. Actual costs compared and the Latest Estimate in PRS(Profitability Reporting System).
  • D. Estimated baseline and Cost Baseline.


Answer : B

In which case is it required to update/change the Cost Baseline?

  • A. In case of roll-out delays affecting the original cost plan.
  • B. In case of a change in subcontractor prices.
  • C. In case of scope changes supported by a legal binding document.
  • D. In case a risk is materialized.


Answer : C

What are the components of Latest Estimate in PRS(Profitability Reporting System)?

  • A. Sales, Cost of Sales and Gross Profit.
  • B. Sales, Volumes and Cost of Sales.
  • C. Actual results of the Previous Period.
  • D. Baseline, ETC and EAC.


Answer : A

What is the duration of a Short Term Planning (STP) period?

  • A. 1 Month.
  • B. 6 Months.
  • C. 1 Quarter.
  • D. 1 Year.


Answer : B

What is the impact to increasing Contingency Reserves due to new project Risks identified?

  • A. Reduction of Gross Margin.
  • B. Change Management process must be triggered.
  • C. New Baseline must be approved by Revenue Recognition Board.
  • D. Site cost will increase.


Answer : A

What are key components of EVM methodology?

  • A. Planned Value, Earned Value and Actual Cost.
  • B. Planned Cost, Revenue and Gross Margin.
  • C. Baseline Costs, Estimated at Completion and Estimate to Complete.
  • D. As Sold Cost Estimates, Baseline and EAC.


Answer : A

When should non-quality costs be analysed?

  • A. At project's end as part of the preparation for lessons learned and post calculation.
  • B. At the beginning of the project as part of risk planning.
  • C. Regularly, in order to identify root causes and take corrective actions.
  • D. Never, non-quality costs are product related and analyzed on global level.


Answer : C

Which of these Key Performance Indicators (KPI) supports the identification of possible cost overruns?

  • A. Project Cost Adherence (PCA).
  • B. Rollout Accuracy (RA).
  • C. Site Invoice Lead Time (SILT).
  • D. Project Asset Rotation Days (PARD).


Answer : C

How frequently is an update of the "Cost Estimation at Completion" required?

  • A. Each time there is a change in the scope of work.
  • B. Each time there is a change in the schedule or scope of work.
  • C. At least once per month, preferably before period end.
  • D. Every quarter before PRS(Profitability Reporting System) results are published.


Answer : C

By which trigger is Accrued Cost transferred to Actual Cost?

  • A. Subcontractor invoice received.
  • B. Internal acceptance issued.
  • C. Goods Receipt (GR) booked.
  • D. Customer acceptance received.


Answer : C