BCS RE18 - BCS Practitioner Certificate in Requirements Engineering 2018 Exam
Page: 3 / 8
Total 40 questions
Question #11 (Topic: Exam A)
A business analyst is in the process of validating a set of requirements produced for a new business initiative and the following needs agreement:
That the requirements...
1) Are within the scope of the project.
2) Can be verified when they have been implemented.
3) Express business needs clearly and correctly.
Who is responsible for this agreement?
That the requirements...
1) Are within the scope of the project.
2) Can be verified when they have been implemented.
3) Express business needs clearly and correctly.
Who is responsible for this agreement?
A. Developers, business owners, business analyst.
B. Developers, testers, business sponsor.
C. Testers, business owners, business analyst.
D. Testers, business owners, business sponsor.
Answer: A
Question #12 (Topic: Exam A)
A set of requirements for a new online health information portal have been prioritized using MoSCoW:
REQ#1: (S)
REQ#2: (C)
REQ#3: (S)
REQ#4: (M)
REQ#5: (M)
REQ#6: (C)
REQ#7: (W)
Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule.
Which two requirements will now be added to the first iteration build?
REQ#1: (S)
REQ#2: (C)
REQ#3: (S)
REQ#4: (M)
REQ#5: (M)
REQ#6: (C)
REQ#7: (W)
Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule.
Which two requirements will now be added to the first iteration build?
A. REQ#1 and REQ#3
B. REQ#2 and REQ#6
C. REQ#4 and REQ#5
D. REQ#6 and REQ#7
Answer: A
Question #13 (Topic: Exam A)
A project team has decided that it wishes to adopt an agile/iterative approach to a development project. The following principles have been agreed upon to guide the selection of elicitation techniques:
1) We will embrace the evolutionary and re-factoring principles of iterative development in our approach to requirements elicitation.
2) We need to build a broad (but basic) understanding of how teams work together in the current business situation.
3) We need to build strong personal relationships to ensure we can instil empowerment and collaboration in the team.
Which of the following sets of elicitation techniques would support all these principles?
1) We will embrace the evolutionary and re-factoring principles of iterative development in our approach to requirements elicitation.
2) We need to build a broad (but basic) understanding of how teams work together in the current business situation.
3) We need to build strong personal relationships to ensure we can instil empowerment and collaboration in the team.
Which of the following sets of elicitation techniques would support all these principles?
A. Interviews, prototyping, scenario analysis.
B. Interviews, workshops, observation.
C. Prototyping, scenario analysis, document analysis.
D. Scenario analysis, observation, survey.
Answer: B
Question #14 (Topic: Exam A)
A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'.
What element of requirements management will offer this?
What element of requirements management will offer this?
A. Change control
B. Configuration control
C. Configuration management
D. Software support
Answer: A
Question #15 (Topic: Exam A)
A business analyst working on a project has identified:
3 requirements for which there is a workaround and the users can live without;
2 requirements that the users can live without for now;
15 requirements which, if not delivered, will make the solution unworkable or useless.
When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
3 requirements for which there is a workaround and the users can live without;
2 requirements that the users can live without for now;
15 requirements which, if not delivered, will make the solution unworkable or useless.
When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
A. M
B. S
C. C
D. W
Answer: D