Question #1 (Topic: Single Topic)
Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should
happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the
information distribution process in your program?
happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the
information distribution process in your program?
A. Change requests
B. Earned value management results
C. Stakeholder analysis plan
D. Performance reports
Answer: C
Question #2 (Topic: Single Topic)
What is the formula to determine earned value (EV) for a program?
A. Percent complete times percent remaining in the program
B. Percent completes time the program cost estimate
C. Percent complete times the program budget at completion
D. Percent complete times the program cost of labor and materials
Answer: C
Question #3 (Topic: Single Topic)
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has
set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team.
This requirement for four licensed electricians is an example of which one of the following terms?
set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team.
This requirement for four licensed electricians is an example of which one of the following terms?
A. Screening system
B. Scoring model
C. Vendor analysis requirements
D. Evaluation criteria
Answer: A
Question #4 (Topic: Single Topic)
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived
threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
A. Requirements document
B. Project charter
C. Business case
D. Scope statement
Answer: C
Question #5 (Topic: Single Topic)
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and
according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If
the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that
the work is done accordingly to scope?
according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If
the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that
the work is done accordingly to scope?
A. Quality control
B. Scope verification
C. Quality assurance
D. Planning
Answer: A