Question #6 (Topic: Exam A)
Adding acceptance criteria to each Product Backlog item is a practice many Scrum Teams find useful. Is it the Product Owner’s responsibility to write all of the acceptance criteria for each Product Backlog Items?
A. Yes. the Product Owner is responsible for adding acceptance criteria to Product Backlog items.
B. No, acceptance criteria should be written by the Developers completing the work.
C. It depends, the Product Owner is accountable for clearly communicating Product Backlog items but they may delegate the responsibility of writing acceptance criteria to others, or they may do the work themselves.
Answer: C
Question #7 (Topic: Exam A)
Given only the information in the following three statements:
Product A has a greater potential market than Product B.
Product A has lower customer satisfaction than Product B.
Product B produces more revenue at the present time.
Which investment strategies should you consider for these two products?
Product A has a greater potential market than Product B.
Product A has lower customer satisfaction than Product B.
Product B produces more revenue at the present time.
Which investment strategies should you consider for these two products?
A. For Doth products, continually measure the impact of any new investments or marketing
B. Invest in Product A to increase its market share, customer satisfaction, and revenue
C. Investigate an increase in marketing for Product B to grow its market share
D. All of the above
Answer: D
Question #8 (Topic: Exam A)
Complete this sentence: The more uncertain you are about customer needs or market desires _____________ (Choose two.)
A. the more likely it is that you should invest in a different product.
B. the more important a risk management plan becomes.
C. the smaller each release should be.
D. the more you should focus on validating customer needs.
Answer: CD
Question #9 (Topic: Exam A)
The primary accountability of a Product Owner is:
A. Writing user Stories that the Scrum Team can fully understand
B. Maximizing the value of the work that the Scrum Team delivers
C. Interfacing between the Developers and the customers
D. Managing the Product Backlog
Answer: B
Question #10 (Topic: Exam A)
Which of the following statements about the Product Backlog are true? (Choose two.)
A. All Product Backlog items must be expressed as user stones.
B. The Product Backlog represents the input of all stakeholders and eliminates any need for the Developers to speak to stakeholders.
C. All Product Backlog items must be identified before the first Sprint begins.
D. The Product Backlog should be visible to the Scrum Team and stakeholders.
E. The Product Backlog is ordered by the Product Owner.
F. Only the Product Owner can place items on the Product Backlog.
Answer: DE