Scrum PSM I - Professional Scrum Master I Exam

Question #11 (Topic: Single Topic)
Which of the following is required by Scrum?
A. Sprint Retrospective. B. Members must be stand up at the Daily Scrum. C. Sprint Burndown Chart. D. Release planning. E. All of the above.
Answer: E
Question #12 (Topic: Single Topic)
What is the purpose of a Sprint Review?
A. To take time to judge the validity of the project. B. To inspect the product Increment with the stakeholders and collect feedback on next steps. C. To review the Scrum Teamג€™s activities and processes during the Sprint. D. To build team sprint.
Answer: B
Question #13 (Topic: Single Topic)
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
A. The Project Manager. B. The Development Team. C. The Scrum Team. D. The Product Owner.
Answer: B
Question #14 (Topic: Single Topic)
Who must attend the Daily Scrum?
A. The Scrum Master and Product Owner. B. The Development Team. C. The Development Team and Product Owner. D. The Scrum Team. E. The Development Team and Scrum Master.
Answer: B
Question #15 (Topic: Single Topic)
When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
A. At the Sprint planning meeting. B. During the Daily Scrum. C. Never. All Sprint Backlog Items are ג€ownedג€ by the entire Scrum Team. D. Whenever a team member can accommodate more work.
Answer: C