PRINCE2 PRINCE2 Agile Foundation - PRINCE2 Agile Foundation Exam

Question #1 (Topic: Single Topic)
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.
A. 1 and 2 B. 2 and 3 C. 3 and 4 D. 1 and 4
Answer: C
Question #2 (Topic: Single Topic)
Which is a key objective of running a workshop?
A. To make daily progress visible to the delivery team and key stakeholders B. To encourage collaboration and create the defined outputs from the event C. To communicate decisions to the wider stakeholder community D. To make day-to-day decisions on behalf of the delivery team within a sprint
Answer: B
Question #3 (Topic: Single Topic)
Which statement about the waterfall methodology definition is CORRECT?
A. It states that deadlines should not be moved B. It has distinct goals for each stage of development C. It is a behavior that involves making things transparent D. It promotes the use of experiments carried out in a scientific way
Answer: B
Question #4 (Topic: Single Topic)
How should product-based planning be used as part of PRINCE2 Agile?
A. To track progress against the team plan B. To create the project plan using empiricism C. To enable team planning to be predictive D. To plan by focusing on the features required
Answer: D
Question #5 (Topic: Single Topic)
Which statement about the 'directing a project' process is CORRECT?
A. The project board should attend regular project progress meetings B. The project board should make decisions based on the Agilometer risks C. A project board member should fulfill the product owner role within a delivery team D. The project board should increase the stage-level time tolerance
Answer: C
Download Exam
Page: 1 / 19
Total 93 questions