BCS PRF - PRINCE2 Foundation Exam

Question #1 (Topic: Topic 1)
When considering risks, which describes an opportunity in a project?
A. An uncertain event that could have a negative impact on objectives B. An uncertain event that could have a favourable impact on objectives C. An event that has occurred resulting in a negative impact on objectives D. An event that has occurred resulting in a favourable impact on objectives
Answer: B
Question #2 (Topic: Topic 1)
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits
laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should
be referred to the Project Manager down by the Project Board.
A. Only 1 is true B. Only 2 is true C. Both 1 and 2 are true D. Neither 1 or 2 are true
Answer: C
Question #3 (Topic: Topic 1)
Which may be funded from a risk budget?
A. Corrections due to off-specifications B. Impact analysis of requests for change C. Implementation of a fallback plan D. Preparation of the Risk Management Strategy
Answer: C
Question #4 (Topic: Topic 1)
What is the first task of product-based planning?
A. Produce the Initiation Stage Plan B. Write the Project Product Description C. Identify dependencies D. Create the product breakdown structure
Answer: B
Question #5 (Topic: Topic 1)
How many tasks does the product-based planning technique describe?
A. One B. Two C. Three D. Four
Answer: D
Download Exam
Page: 1 / 49
Total 244 questions