Question #6 (Topic: Single Topic)
During iteration planning, it was determined that an epic should be decomposed.
What was the determining factor?
A. Size and priority B. Minimum marketable features C. Release plan D. Sprint mapping
Answer: A
Question #7 (Topic: Single Topic)
What should a scrum master do when one team member falls behind in their tasks?
A. Move the task to another team member who has spare capacity in the sprint B. Ask the team for suggestions C. Privately offer the team member encouragement to meet task commitments D. Notify the product owner
Answer: B
Question #8 (Topic: Single Topic)
A newly formed scrum team wants to foster an environment for transparency and experimentation. The team decides to use a Kanban board to record and track
encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future.
Over time, what will be the result of this approach?
A. Kaizen B. Specific, measurable, assignable, realistic, and time-based (SMART) goals C. Key performance indicators (KPIs) D. Muda
Answer: A
Question #9 (Topic: Single Topic)
A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate.
What should be the agile project leader do?
A. Bring up the new memberג€™s impediments at the next meeting to demonstrate team support of input B. Assure the new member that inputs on impediments are valued, and demonstrate this at the next meeting C. Have a senior leader work with the new member to avoid a negative impact on team productivity D. Privately work with the new member to address any impediments
Answer: B
Question #10 (Topic: Single Topic)
During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.
What should the scrum master do?
A. Ask the lead developer to identify a solution, and then share the details with the team B. Ask a technical manager or architect to determine a solution to the problem C. Work with the product owner to add a spike to the next sprint to identify a solution D. Create a collaborative team environment so that the team can explore a solution together
Answer: D