Question #11 (Topic: Exam A)
You are replacing the access layer of a customer data center network that uses VMware NSX. The customer has identified several subnets outside the VMware platform to which the customer would like to add overlay routing.
What high-level plan works for this customer?
What high-level plan works for this customer?
A. Proposing CX switches and a Fabric Composer plug-in to Morpheus VM Essentials, which will create an integrated overlay fabric for all subnets
B. Proposing CX switches and a Fabric Composer plug-in. which will enable the CX switches to add the subnets in question to the same overlay used by NSX
C. Proposing CX switches that use EVPN VXLAN to provide a separate overlay fabric for the subnets in question
D. Proposing CX switches, which will integrate with NSX to provide the desired functionality provided that the customer also add NSX licenses
Answer: C
Question #12 (Topic: Exam A)
Identify the documentation resources for finding validated information that assists the architect in designing the solution (Choose two.)
A. Product reviews (cnet, networkworld)
B. Configuration guides
C. Data sheets
D. LinkedIn
E. Competitive documentation
Answer: BC
Question #13 (Topic: Exam A)
Your long-time customer has just acquired a company with 3,500 employees and they are planning on bringing the new data center sites up to their standards. They have asked for a bill of materials given only locations and port counts at the data center sites.
What are valid assumptions that should be documented in the proposal? (Choose two.)
What are valid assumptions that should be documented in the proposal? (Choose two.)
A. The implementation project manager will be from the acquired company
B. The acquired company's existing contract staff will be hired as full-time employees
C. The IP segments in the existing data centers will remain the same as the acquired company.
D. The acquired company’s physical data cable plant at the new location will meet the technical requirements of the new solution.
E. The power at the acquired company's data center locations is sufficient for the proposed equipment.
Answer: DE
Question #14 (Topic: Exam A)
A customer wants to convert as many upfront costs into smaller ongoing bills as possible. For which components can HPE GreenLake for Networking provide recurring billing?
A. Hardware and support, but not software
B. Software and support, but not hardware
C. Hardware software, and support
D. Hardware and software, but not support
Answer: C
Question #15 (Topic: Exam A)
Your long-time customer has just acquired a company and they are planning on bringing the new data center sites up to their standards. They have asked for a bill of materials given only locations and port counts at the data center sites.
What are valid assumptions that should be documented in the proposal? (Choose two.)
What are valid assumptions that should be documented in the proposal? (Choose two.)
A. The acquired company's full-time staff will be converted to contractors.
B. The acquired company’s IP schema in the existing data centers will be converted to IPv6.
C. The project will be funded by the capital budget of the acquired company.
D. The acquired company’s data center cooling plant allows for the back-to-front airflow preferred by your customer.
E. The acquired company's data center racks are sufficient for the new equipment and will be reused.
Answer: DE