Question #11 (Topic: Exam A)
Which page in the Dell Data Domain System Manager should an implementation engineer open to confirm model, DDOS version, uptime, and serial numbers?
A. Dashboard > Overview
B. Maintenance > System
C. Data Management > File System
D. Hardware > System
Answer: B
Question #12 (Topic: Exam A)
A customer is adding an ES40 to a Dell PowerProtect DD9410 for storage expansion.
When cabling SAS cables to the controller what should the technician do?
When cabling SAS cables to the controller what should the technician do?
A. Ensure there is enough slack for the controller to fully extended out of the rack.
B. Bypass the cable management arm and connect directly to the controller.
C. Ensure that cables are pulled tight to dress it properly.
D. Allow all cables to hang freely for more flexibility.
Answer: A
Question #13 (Topic: Exam A)
An implementation engineer is performing an initial configuration of Cloud Tier on a Dell PowerProtect Data Domain Virtual Edition (DDVE) appliance.
What must they do before implementing this feature?
What must they do before implementing this feature?
A. Replication must be disabled
B. The file system must be disabled
C. Encryption must be enabled
D. Security policy must be enabled
Answer: B
Question #14 (Topic: Exam A)
A deployment engineer is configuring a syslog server on a Dell PowerProtect Data Domain appliance. They must ensure that all logs are correctly received by the syslog server.
What must be verified to ensure this will work as expected?
What must be verified to ensure this will work as expected?
A. System alerts must be configured
B. DDOS version must be 7.13 or higher
C. Port 514/UDP must be open in the firewall settings
D. SNMP must be enabled
Answer: C
Question #15 (Topic: Exam A)
An implementation engineer is at a customer site and is powering-up the Dell PowerProtect Data Domain DD9910 with three DS600 expansion shelves.
What must be done before powering-up the controller?
What must be done before powering-up the controller?
A. Connect the power cables to the expansion shelves
B. Verify network cables are properly connected
C. Check the system identification button
D. Access the iDRAC console to verify system
Answer: A