GAQM CTIL - Certified Software Tester - Intermediate Level (CSTIL) Exam

Question #11 (Topic: Topic 3)
Which of the following best describes a testing challenge of the application domain of the
routers described?
A. Testing that the receivers PC can store emails routed to it. B. Testing that large organisations can scan incoming files routed to them for viruses. C. Testing that packets are delivered by the routers in the required timescales. D. Testing that files can be sent in any language.
Answer: C
Question #12 (Topic: Topic 3)
Which of the following would be applicable as part of a test policy for testing these types of
systems?
a)Systems must be tested for compliance to industry standard routing protocols.
b)Testing for the latest upgrade will require testing of increased network traffic of 100%.
c)Testing for the fix will require the use of dynamic analysis tools.
d)Releases will not be made if systems have any high priority defects outstanding.
A. a and b. B. a and d. C. b and c. D. b and d.
Answer: B
Question #13 (Topic: Topic 3)
Which of the following reviews would you recommend to address this issue?
A. A walkthrough of the requirement specification, to check for errors. B. A management review of defects logged and cleared to see if defects are being addressed correctly. C. A technical review of the industry standard routing protocols to see if they have inaccuracies in them. D. An inspection of the code for this part of the functionality to try to localise the defective parts of the code.
Answer: D
Question #14 (Topic: Topic 3)
You need to test that the rules have been correctly set up in the configuration table,
according to the specification. Which one of the following test design techniques would be
most suitable for this?
A. Data flow testing. B. Statement testing. C. Decision table testing. D. Boundary value analysis.
Answer: C
Question #15 (Topic: Topic 3)
When a software defect in a system has been found and fixed, which of the following
activities should be undertaken next?
a.Debugging.
b.Confirmation testing.
c.Regression testing.
d.System testing.
e.Static testing.
A. a and b.
B. b and c.
C. c and d.
D. c and e.
Answer: B Topic 4, Case Study# 4Scenario A bank is upgrading its systems to include an on-line investment service, allowing investors to trade with each other, in a mini-stock market environment. The upgrade will be carried out using Agile development (within the Scrum framework). Here, the iterations are referred to as Sprints. For each Sprint the required functionality will be defined as a set of user-stories. The user stories are typically 1-2 lines long, indicating what the business wants the system to do. These user stories will be built then tested. 1) Creation of the mini-stock market trading environment. 2) Creation of additional front-end enhancements. 3) Linking to stock exchange for pricing. You are the test manager. You lead a team of 4 testers, and there are 6 developers. Your team has worked on Agile projects previously, and on average, Sprints usually last 4 weeks. At the end of all Sprints, a full end to end test is carried out. This is called the E2E test phase. You are worried that 4 weeks will not be sufficient time for the first Sprint. You have decided to conduct a Risk Management exercise before the project starts.