ASQ CSSGB - Six Sigma Green Belt Exam
Page: 3 / 29
Total 144 questions
Question #11 (Topic: Exam A)
A periodic time frame can be used to arrange for Control Limit and Center Line calculations with good SPC implementation in a process.
A. True
B. False
Answer: A
Question #12 (Topic: Exam A)
The data on SPC charts are typically constructed such that they have the most recent data point on the right hand side.
A. True
B. False
Answer: A
Question #13 (Topic: Exam A)
Which statement(s) describe an undesirable situation when implementing SPC?
A. The lower Control Limit for the R chart is equal to zero
B. Attempt to use SPC for tracking transaction times at a warehouse
C. A process is in Statistical Control before implementation of SPC
D. The Control Limits are wider than the customer specification limits
Answer: D
Question #14 (Topic: Exam A)
If a process has Outliers which pair of charts is most preferable if subgroups will exist for the Continuous Data?
A. Individual—Moving Range
B. Xbar-R Charts
C. Xbar-S Charts
D. nP and P Charts
Answer: B
Question #15 (Topic: Exam A)
After a Belt has put data through the smoothing process which chart would be used to look for trends in the data?
A. Moving Average Chart
B. Multi-Vari Chart
C. X bar Chart
D. Pareto Chart
Answer: A