Question #11 (Topic: Exam A)
What is required when a Scrum Team says a Product Backlog item is done?
A. The item has been developed and tested
B. The item has been deployed to the production environment
C. The item meets the Scrum Team's understanding of the Definition of Done
D. The item meets the Definition of Done provided by the Product Owner
Answer: C
Question #12 (Topic: Exam A)
When the goal, scope and product domain are not understood by the Scrum Team, the Scrum Master should:
A. direct the Developers to stop working until the Product Owner improves the acceptance criteria.
B. cancel the Sprint and schedule a new Planning meeting.
C. do nothing because this is the responsibility of the Product Owner.
D. facilitate a discussion between the Stakeholders, Product Owner and Developers.
Answer: D
Question #13 (Topic: Exam A)
Which one of the following statements is true regarding the Increment?
A. It must have all of the requirements that need to be in the product before the Product Owner will release it.
B. Is not releasable until the Product Owner determines it is done.
C. It must be in a useable condition and meet the Definition of Done.
D. Is not releasable until it has all of the features to be a Minimally Viable Product.
Answer: B
Question #14 (Topic: Exam A)
What is one accountability of a Scrum Master?
A. Set the budget
B. Provide estimates
C. Improve the Scrum Team's effectiveness
D. Decide when to release the product
Answer: C
Question #15 (Topic: Exam A)
Which of the following is a Scrum Artifact?
A. Definition of Done
B. Sprint Backlog
C. Sprint Goal
D. Sprint Burndown Chart
Answer: B