Question #11 (Topic: )
A periodic time frame can be used to arrange for Control Limit and Center Line calculations
with good SPC implementation in a process.
A. True B. False
Answer: A
Question #12 (Topic: )
The data on SPC charts are typically constructed such that they have the most recent data
point on the right hand side.
A. True B. False
Answer: A
Question #13 (Topic: )
Which statement(s) describe an undesirable situation when implementing SPC?
A. The lower Control Limit for the R chart is equal to zero B. Attempt to use SPC for tracking transaction times at a warehouse C. A process is in Statistical Control before implementation of SPC D. The Control Limits are wider than the customer specification limits
Answer: D
Question #14 (Topic: )
If a process has Outliers which pair of charts is most preferable if subgroups will exist for
the Continuous Data?
A. Individual—Moving Range B. Xbar-R Charts C. Xbar-S Charts D. nP and P Charts
Answer: B
Question #15 (Topic: )
After a Belt has put data through the smoothing process which chart would be used to look
for trends in the data?
A. Moving Average Chart B. Multi-Vari Chart C. X bar Chart D. Pareto Chart
Answer: A