ServiceNow CIS-SPM - Certified Implementation Specialist - Strategic Portfolio Management Exam

Question #11 (Topic: Exam A)
Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.
A. pm_toplevel_project B. project_template_config C. pm_home_page_config D. pm_project
Answer: C
Question #12 (Topic: Exam A)
As a demand manager, you can view an artifact from a demand. What artifacts are part of a demand?
A. Stories, Vulnerability Tasks, Enhancements. B. Project, Defect, Requests. C. Incidents, Problems, Change. D. Decision, Risk, Requirements.
Answer: B
Question #13 (Topic: Exam A)
When creating a project from demand, what related records are moved and copied upon Project Creation?
A. Cost Plan and Assessment. B. Resource Plan and Change Requests. C. Resource Plan and Cost Plan. D. Idea and Demand.
Answer: C
Question #14 (Topic: Exam A)
If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?
A. Front Load. B. Back Load. C. Any. D. Even.
Answer: A
Question #15 (Topic: Exam A)
If the ‘Move project for WIP projects’ property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states? (Choose two.)
A. Work in Progress B. Closed C. Pending D. Open
Answer: AB
Download Exam
Page: 3 / 37