Question #6 (Topic: Single Topic)
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
A. create the project management plan.
B. identify the project objectives.
C. review and update stakeholder engagement.
D. create the schedule baseline.
Answer: C
Question #7 (Topic: Single Topic)
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified.
How many communication channels are available?
How many communication channels are available?
A. 8
B. 18
C. 36
D. 40
Answer: C
Question #8 (Topic: Single Topic)
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to
capture stakeholder interest?
capture stakeholder interest?
A. Review stakeholder register and meeting
B. Data analysis and communication skills
C. Data gathering and data analysis
D. Communication skills and cultural awareness
Answer: D
Question #9 (Topic: Single Topic)
Select three processes that are associated with Project Schedule Management? (Choose three.)
A. Define Activities
B. Plan Resource Management
C. Estimate Activity Durations
D. Develop Schedule
E. Acquire Resources
Answer: ACD
Question #10 (Topic: Single Topic)
What are the project management processes associated with project quality management?
A. Plan Quality Management, Manage Quality, and Control Quality
B. Plan Quality Management, Manage Quality, and Cost of Quality
C. Manage Quality, Customer Satisfaction, and Control Quality
D. Customer Satisfaction, Control Quality, and Continuous Improvement
Answer: A