IBM C9030-622 - System z Business Resiliency Solution Selling Exam
Page: 3 / 10
Total 50 questions
Question #11 (Topic: )
Which of the following actions will have the greatest impact on future zEnterprise business
recovery processes?
recovery processes?
A. Implementing I/T optimization
B. Planning for GDPS Active/Active solution
C. Using zBX for distributed server recovery
D. Implementing a Cloud on System z solution
Answer: B
Question #12 (Topic: )
A customer is debating which platform to choose to run their new application workload.
Which of the following will assist customer to confirm their platform of choice?
Which of the following will assist customer to confirm their platform of choice?
A. CP3000 study
B. Fit for Purpose (FFP) study
C. High Availability assessment
D. Application design review workshop
Answer: B
Question #13 (Topic: )
What type of coupling links are required to support distances greater than 10 KM?
A. ICM3
B. ICB4
C. PSIFB LR 1x
D. PSIFB SR 12X
Answer: C
Question #14 (Topic: )
Which of the following most completely determines the cost of an outage?
A. Damage to market reputation
B. Loss of loyal customer business
C. Reduction in worker productively
D. Lost revenue and recovery expenses
Answer: D
Question #15 (Topic: )
A customer is implementing a GDPS/PPRC solution and is concerned about building skills
for their staff. Which of the following is an appropriate response?
for their staff. Which of the following is an appropriate response?
A. IBM Tivoli System Automation Manual
B. IBM Lab Services provides transition staffing
C. System zTechnical events offer customized instruction
D. Transition education is included in a typical services solution
Answer: D