Question #1 (Topic: )
A business wants to make sure that when an item within an order is not available at
localstore or regional distribution centers, the item should be sourced from a central
warehouse.
How can this be accomplished?
localstore or regional distribution centers, the item should be sourced from a central
warehouse.
How can this be accomplished?
A. Enable the "Fulfill from all ship nodes" configuration in the Applications Manager
B. Ensure that the central warehouse belongs to a central region created in the Applications Manager
C. Ensure that the central warehouse is configured in a distribution group in the Applications Manager
D. Make use of the backorder against the highest priority ship node rule in the document- specific fulfillment rule
Answer: C
Question #2 (Topic: )
n the out-of-the-box order fulfillment pipeline, what does the "Consolidate toshipment"
transaction do?
transaction do?
A. Either consolidates to existing shipment or creates a new shipment
B. Always creates a new shipment for a Given Order release
C. Shipment will not be created if the given order release cannot be included in an existingshipment
D. Always finds an existing shipment into which the Release can be included
Answer: B
Question #3 (Topic: )
Two organizations of a company have the same item identifier for two different physical
items and the company does not have a common item ID for the two items. How should the
implementation professional define the Catalog Organization?
items and the company does not have a common item ID for the two items. How should the
implementation professional define the Catalog Organization?
A. Defined at the highest level in the organization hierarchy
B. Defined at the lower level in the organization hierarchy C Defined to inherit properties from pricing organization
C. Defined to be able to modify configuration groups at inventory level
Answer: B
Question #4 (Topic: )
Application server data source connection pooling needs tobe enabled for an IBM Sterling
Order Management V9.4 application deployed on Oracle WebLogic Application Server 12c
and Oracle Database 11g (11.2.0.4).
Which configuration will enable data source connection pooling?
Order Management V9.4 application deployed on Oracle WebLogic Application Server 12c
and Oracle Database 11g (11.2.0.4).
Which configuration will enable data source connection pooling?
A. Add "jdbcService oraclePool datasource=<datasourceName>1' in $INSTALL_DIR/properties/customer_overrides properties and Update JVM argument to - Dvendor=weblogic
B. Add "jdbcService.oraclePool.datasource=<datasourceName>" in $INSTALL_DIR/properties/jdbc.properties and Update JVM argument to - Dvendor=weblogic12
C. Add "jdbcService.oraclePool.datasource=<datasourceName>" in $INSTALL_DIR/properties/jdbc.properties and Update JVM argument to - Dvendor=weblogic
D. Add "jdbcService.oraclePool.datasource=<datasourceName>" in $INSTALL_DIR/properties/customer_overrides.properties and Update JVM argument to - Dvendor=weblogic12
Answer: A
Question #5 (Topic: )
A retailer has a requirement to group certain regular items together to form a parent item.
The inventory is maintained only at the parent item level and not for the components. The
parent item will be sold as an individual item, with all the components.
How should the implementation professional configure the item type to support the
retailer's requirement?
The inventory is maintained only at the parent item level and not for the components. The
parent item will be sold as an individual item, with all the components.
How should the implementation professional configure the item type to support the
retailer's requirement?
A. Logical Kit
B. Dynamic Physical Kit C Physical Kit
C. Bundle Items
Answer: C