Question #1 (Topic: )
In RQM version 3, what can have execution records? (Choose two.)
A. Test Plan
B. Test Case
C. Test Suite
D. Test Script
Answer: B,C
Question #2 (Topic: )
Which database servers are supported by the Jazz Team Server?
A. IBM DB2, Derby, MySQL, Microsoft SQL Server
B. Microsoft SQL Server, Microsoft Access, Derby, IBM DB2
C. Derby, IBM DB2, Microsoft SQL Server,Oracle Database
D. IBM DB2, Software AG Adabas, Microsoft SQL Server, Oracle Database
Answer: C
Question #3 (Topic: )
Which sequence represents the flow of steps that developers use to collaborate with regard
to Jazz source control?
to Jazz source control?
A. checkout, checkin, baseline
B. checkin, deliver, accept
C. accept, checkout, deliver
D. rebase, checkout, checkin, deliver
Answer: B
Question #4 (Topic: )
What are two capabilities provided by the Lifecycle Project Administration (LPA)
application?
application?
A. Create a lifecycle project from a predefined template
B. Configure email setting for notification when a work item is updated
C. Import process template that can be used for lifecycle projects
D. Define members to all of the project areas that belong to a lifecycle project
E. Registerapplications to add to the Jazz Team Server environment
Answer: A
Question #5 (Topic: )
Which three Reporting solutions are supported by CLM 2012? (Choose three.)
A. BIRT
B. RRDI
C. Open Reports
D. Crystal Reports
E. RRDG
Answer: A,B,E