During thedevelopment and test phase of a project, the team's process requires that the architect check all changes made for a defect to ensure that the work is in-line with the solution design principals. Using the work items feature available with CLM, which threesteps assist in making this possible? (Choose three.)

  • A. define a role of "Architect" and assign it to the appropriate users
  • B. for the relevant transition in the work item lifecycle, add a precondition for a "Required approval" by the architect
  • C. create a work item template containing the values that are applied when an architect has reviewed a work item
  • D. add a new state for the work item called "Requiring Architecture Approval", where the lifecycle will pause until the architect approves
  • E. insert anew Boolean field in all work items to indicate whether or not the work item has been checked by an architect


Answer : A,B,D

Which two statements are true about working with client access licenses for CLM? (Choose two.)

  • A. Licenses mustbe applied to a user for them to access the application capabilities.
  • B. Licenses grant automatic access to a project area.
  • C. Licenses are role-based.
  • D. A license cannot be manually re-assigned to another user for four hours.
  • E. A purchased license cannot be added to a server running trial licenses.


Answer : A,C

Which license type is used to support extended users such as customers, support personnel, or extended community members who want to modify work items and observe project progress?

  • A. Contributor
  • B. Stakeholder
  • C. Developer
  • D. Developer for Workgroups


Answer : B

Where must client access licenses for CLM be installed?

  • A. the Jazz Team Server
  • B. the Eclipse client
  • C. the Visual Studio client
  • D. the client webbrowser
  • E. the database server


Answer : A

When completing a plan item, which role does the test team provide?

  • A. creates an iteration plan and chooses which plan items to target for the first iteration
  • B. reviews the plan items that aretargeted for the iteration and the related high-level requirements, and creates detailed requirements
  • C. elaborates the test cases that are associated with the development tasks
  • D. checks in their change sets and runs personal builds to test the changes intheir own workspaces
  • E. runs a team build, reviews the results, and tags the build as ready for testing


Answer : C

When performing a design review in Rational Software Architect Design Manager, a reviewer can add and associate commentswith _____. (Choose three.)

  • A. any diagrams contained in the solution model
  • B. any components contained in the solution model
  • C. related RTC work items reflecting non-functional requirements
  • D. the work item review/approval lifecycle in place for the project
  • E. the packages and package hierarchy used in the model


Answer : A,B,E

What is Rational Reporting for Development Intelligence (RRDI)?

  • A. a Web 2.0 based solution that can quickly create queries, reports, and dashboards using severalformats including PDF or MS Excel
  • B. custom reports, queries, and dashboards displayed within CLM
  • C. a desktop application that generates high quality, formal documents with flexible formatting capability
  • D. parameter-driven reports that provide limited customization capabilities


Answer : A

What are two valid usage scenarios for integrating Rational BuildForge with CLM 4.0.1?
(Choose two.)

  • A. start BuildForge jobs without leaving the RTC UI
  • B. for regression testing
  • C. track, control, and report on the execution of complex tasks distributed over multiple lab resources
  • D. create process definitions of how a build has to be done


Answer : A,C

Which three actions can be performed when reviewing a Rational Software Architectmodel that has been published to Rational Software Architect Design Manager? (Choose three.)

  • A. annotating a diagram in the published model
  • B. changing the color of a model element that is believed to be incorrect
  • C. initiating an in-line discussion aboutthe structure of a class
  • D. adding a comment concerning the package structure within the model
  • E. creating a copy of the model and modifying the package structure


Answer : A,C,D

What is the fundamental unit of source control modification?

  • A. change sets
  • B. work items
  • C. components
  • D. streams
  • E. workspaces


Answer : A

Which important CLM themes are covered by the "Money that Matters" scenario?

  • A. realizing use cases and transforming diagrams to code
  • B. aligning releaseplans, test plans, and requirements collections
  • C. functional test plans and automated functional testing
  • D. deployment planning and source code reviews


Answer : B

Which ALM imperative helps teams understand which requirements areaffected by defects?

  • A. Real-time Planning
  • B. Lifecycle Traceability
  • C. In-context Collaboration
  • D. Development Intelligence


Answer : B

Which ALM imperative helps improve the team dynamic and refine toward greater efficiencies?

  • A. Real-time Planning
  • B. Lifecycle Traceability
  • C. In-context Collaboration
  • D. Continuous Process Improvement


Answer : D

Which type of server can act as a floating license server for CLM floating client access licenses?

  • A. any Team Concert (/ccm) server
  • B. any FlexLM server
  • C. any CLM application server
  • D. a database server
  • E. a Jazz Team Server


Answer : E

Which statement is true about the reporting capability within RTC?

  • A. RDDI is used for reporting across a project area inRTC.
  • B. RRDI is a cross-repository reporting server that can generate reports.
  • C. Document generation is provided upon login to RTC.
  • D. Reporting capabilities can be enabled from each user's profile.


Answer : B