Question #11 (Topic: )
What should be considered when voiding a receipt record in IBM Maximo Asset
Management V7.5?
Management V7.5?
A. Service receiptscannotbe voided.
B. A receipt can be voided for a partial quantity.
C. Receipts for returned itemscannotbe voided.
D. Only receipts for non-rotating items can be voided.
Answer: C
Question #12 (Topic: )
If a UFO request requires more than one transaction to satisfy the quantity, which cost will
be displayed for the work order record?
be displayed for the work order record?
A. Lesser
B. Greater
C. Average
D. Standard
Answer: C
Question #13 (Topic: )
Which statement about an operating location is true?
A. A location can be in a network and a hierarchy.
B. A location in a network must have multiple children.
C. A location of any type can be associated with a network.
D. A location can be in a network or a hierarchy, but not both.
Answer: C
Question #14 (Topic: )
Which application is used to create a shipment?
A. Receiving
B. Item Master
C. Inventory Usage
D. Issues and Transfers
Answer: A
Question #15 (Topic: )
How is the seven day work view updated in the Assignment Manager application?
A. Modify Availability
B. Select a new Craft
C. Select a new Work Date
D. Change the Scheduled Start Date
Answer: B