SAP Certified Application Associate - Planning and GATP in SAP SCM APO 7.0 EHP1 v6.0 (C_TSCM44_65)

Page:    1 / 6   
Total 84 questions

After the APO-PP/DS production planning run, your customer notices that planned orders created in APO have not been transferred to ECC. Distribution definitions are maintained.
The requirement objects are sales orders only.
What should you check to resolve this issue?
Note: There are 3 correct answers to this question.

  • A. APO qRFC monitor: Evaluate the system message.
  • B. ECC transaction CFC9: Change transfer for planned orders needs to be set to "BTE transfer (immediately)".
  • C. APO product master: The PP/DS horizon must be large enough to include the sales orders.
  • D. ECC transaction CFM5: The planned orders need to be in at least one active integration model.
  • E. APO global settings in Customizing: Transfer of in-house production to ECC must be supported.


Answer : A,D,E

Using the APO Core Interface, which of the following ECC master data objects are mapped to APO locations?
Note: There are 3 correct answers to this question.

  • A. Distribution center
  • B. Work center
  • C. Production line
  • D. MRP area
  • E. Vendor


Answer : A,D,E

What must be fulfilled for a successful initial transfer of a work center via the APO Core
Interface?
Note: There are 2 correct answers to this question.

  • A. The "relevant to finite scheduling" indicator must be set in the work center.
  • B. An active integration model that contains the work center must exist.
  • C. The resource category must be set to "production".
  • D. The capacity planner group of the work center must be defined in APO.
  • E. Each work center capacity category must be selected separately and transferred via APO CIF.


Answer : A,D

There are fields in the APO product master that are not CIF-relevant.
How can you ensure that these fields can also be maintained systematically?
Note: There are 2 correct answers to this question.

  • A. Use append structures in the material master and transfer these fields using BAdIs.
  • B. Use transport requests from ECC to APO.
  • C. Use master data management (MDM).
  • D. Use a mass maintenance transaction locally in APO.


Answer : A,D

In the context of external procurement, which of the following master data objects are transferred via CIF?
Note: There are 3 correct answers to this question.

  • A. Quota arrangement
  • B. Scheduling agreement
  • C. Source list
  • D. Purchasing info record
  • E. Contract


Answer : B,D,E

Which of the following steps are necessary to generate an RFC connection that can be used for the APO Core Interface?
Note: There are 3 correct answers to this question.
A. Create the necessary IDocs definition initially
B. Assign RFC user to the RFC destination

C. Specify SAP APO release -
D. Assign applications to asynchronous qRFC
E. Assign logical system to a client



Answer : B,C,E Topic 8, Demand Planning (DP)

Why do you need to create planned independent requirements (PIRs) based on DP forecast data?
Note: There are 3 correct answers to this question.

  • A. For the GATP check against ATP time series
  • B. For the GATP check against PIRs
  • C. For the CTP check
  • D. For planning in SNP or PP/DS
  • E. For transferring to SAP ECC Demand Management for ECC MRP planning


Answer : B,D,E

Various background jobs can be scheduled in DP.
What is the correct configuration sequence when scheduling a background job in DP?

  • A. To create proportional factors you need a profile, an activity, and a job.
  • B. To run a macro you need a profile, an activity, and a job.
  • C. To run a forecast you need a profile, an activity, and a job.
  • D. To run a release you need an activity and a job.


Answer : C

How does the system handle data with consistent planning in DP?
Note: There are 3 correct answers to this question.

  • A. It keeps the data for one key figure consistent at all levels.
  • B. It keeps data in the internal BW and liveCache consistent.
  • C. It stores data consistently in aggregates and at the lowest level.
  • D. It keeps data for different key figures consistent at all levels.
  • E. It keeps data for different characteristic value combinations consistent.


Answer : A,C,E

How do you replace an old product with a new one in DP?
Note: There are 2 correct answers to this question.

  • A. Use GATP rules
  • B. Use realignment
  • C. Use form fit function classes
  • D. Create an interchangeability group
  • E. Create a like profile


Answer : A,E

A customer in the soft drinks industry wants to use promotions in DP.
If they plan a promotion for bottles, fewer cans will be planned automatically.
What do you need to configure to plan such a promotion?
Note: There are 3 correct answers to this question.

  • A. Set up cannibalization groups.
  • B. Define the link between bottles and cans via macros.
  • C. Set up a macro that adds the promotion value to final sales.
  • D. Specify which characteristics can be used for promotions in the promotion profile.
  • E. Set up a promotion key figure and assign it to the planning area and characteristic.


Answer : A,C,E

When using forecasting in DP, to what can you assign the forecast profile?
Note: There are 2 correct answers to this question.

A. The product master -

B. A product group -

C. The planning book -
D. A characteristic value combination

E. A selection -



Answer : D,E Topic 9, Production Planning (PPDS) and CTP

Production and capacity planning for several products is finished, resulting in finite scheduled and optimized (setup matrix) planned orders.
How can you transfer the original date, quantity, and capacity situation into the production order?

  • A. Convert the planned order into a production order in ECC since execution occurs in ECC shop floor control.
  • B. Activate one of the BAdIs from function module /SAPAPO/CIF_ORDER_EXTRACT.
  • C. Use the APO planning board function "copy optimized planned order into production order".
  • D. Send the conversion trigger from the leading scheduling system APO PP/DS into the execution system.


Answer : D

Which configuration settings are necessary to set up the CTP process successfully?

  • A. PP/DS planning procedure within the product master must be set to "cover dependent requirements immediately" ? The ATP check instruction must allow "start of production"
  • B. PP/DS planning procedure for the production location must be set to "cover dependent requirements immediately" ? The ATP check instruction must allow "start of production"
  • C. PP/DS planning procedure for planning version "000" must be set to "cover dependent requirements immediately" ? The ATP check control must allow "start of production"
  • D. PP/DS planning procedure within the product master must be set to "cover dependent requirements immediately" ? The ATP check control must allow "start of production"


Answer : A

The customer asks about bucket-oriented CTP.
How do you explain bucket-oriented CTP correctly?

  • A. It allows confirmation against SNP capacity key figures.
  • B. It summarizes all requirements within a predefined bucket and does not confirm individual requirements.
  • C. It schedules against bucket capacity instead of confirming against time-continuous capacity.
  • D. It uses lot size rounding profiles to calculate bucket quantities instead of scheduling lot- for-lot.


Answer : C