SAP C_TSCM42_66 - SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 Exam
Page: 2 / 16
Total 80 questions
Question #6 (Topic: )
Which of the following master data can be used with process orders?(Choose three)
A. Serial numbers
B. Master recipes
C. Resources
D. Production/resource tools
E. Production versions
Answer: B,C,E
Question #7 (Topic: )
You want to use the different options for planning in SAP ECC.
What is the correct sequence of the planning procedures?
What is the correct sequence of the planning procedures?
A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
B. Demand management -> Sales and operations planning -> Capacity planning -> Long- term planning -> Material requirements planning
C. Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning
D. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
Answer: A
Question #8 (Topic: )
Which activity can trigger an automatic availability check for the components of a
production order?
production order?
A. Material staging
B. Order rescheduling
C. Order release
D. Goods receipt for a missing part
Answer: C
Question #9 (Topic: )
You want to enhance the system statuses of a production order with user statuses.
How do you do this?
How do you do this?
A. Define the user statuses in the order type-dependent parameters.
B. Define a status profile in Customizing and assign it to the production scheduling profile.
C. Define a status profile in Customizing and assign it to the order type.
D. Define the user statuses in the Customizing table of the system statuses.
Answer: C
Question #10 (Topic: )
The final assembly of a finished product should only be triggered when a customer order
arrives.
Which planning strategy for the finished product do you use?
arrives.
Which planning strategy for the finished product do you use?
A. Planning with make-to-stock (strategy 10)
B. Planning at the assembly level (strategy 70)
C. Planning without final assembly (strategy 50)
D. Planning with final assembly (strategy 40)
Answer: C