Lifecycle Services for Advanced Wireless LAN (LCSAWLAN) v7.0 (650-621)

Page:    1 / 12   
Total 176 questions

Which one of these choices consists of a task or tasks included in the system migration service component of the implement phase?

  • A. Define Requirements for Monitoring Service Level Measurements
  • B. Confirm Project milestones and cutover Roles and Responsibilities
  • C. Determine Project schedule, Develop Resource Plan, Establish Project Budget
  • D. Assess implementation readiness at each site, define timelines for Post-Implementation Testing, Execute Contingency Plans as required
  • E. Verify that escalation path is in place for difficulties with test cases


Answer : D

Which three of these tasks go into developing a migration strategy? (Choose three.)

  • A. Review Low Level Design with Emphasis on Order of Implementation Activities
  • B. Review Migration Plan and Implementation schedule
  • C. Identify Core infrastructure implementation Requirements and Timeline
  • D. Verify High level site-specific installation Requirements
  • E. Develop Test Plan, Test Cases and Execution Methodology
  • F. Define Failure Recovery Procedure and Risk Mitigation Strategy


Answer : A,C,F

Which templates, tools or reference materials are used in the Business case development service component of the prepare phase? (Choose two.)

  • A. Value Assessment Worksheet
  • B. ROI required information checklist
  • C. Financial justification case study
  • D. Preliminary Discovery Document-Gap Analysis
  • E. Income Statement
  • F. Statement of change in financial Position


Answer : B,C

Which of these is a deliverable to the customer in the implement phase?

  • A. WLAN operations Assessment Report
  • B. An Executed WLAN migration plan
  • C. Security Vulnerability and Recommendations Report
  • D. WLAN Location-based Service Assessment Report
  • E. Technology Assessment Report
  • F. WLAN Operations Readiness Assessment Report


Answer : B

During the System acceptance testing, which template is used to capture the network elements to be tested and the tests that will be completed after solution implementation?

  • A. Technical Requirements Document
  • B. High Level Design
  • C. Bridge Traffic Analyzer
  • D. IPCC Enterprise Configuration Checklist
  • E. Network Ready For Use


Answer : E

In the design phase, which tasks is conducted during the creating of a site specific network implementation plan activity?

  • A. Finalize calls flows and Route Plans
  • B. Create Installation, Commission and Network connectivity Test Tasks and Checklist
  • C. Review Customer Remediation Responsibilities
  • D. Determine shipping Dates and Logistics


Answer : B

Which service component within the prepare phase helps to increase the chances that the proposed system will meet the customer requirements and expectations?

  • A. WLAN Wire Network Integration Assessment
  • B. Business Requirements Development
  • C. Technology Strategy Development
  • D. High Level Design Development
  • E. Proof Of Concepts
  • F. Business Case Development


Answer : E

Which of these is a key deliverable in the design phase?

  • A. As-Built Solution Binder, Operations Support Plan Report, Change Management Status Report
  • B. Business Requirements Document, Preliminary Discovery Document, Technology Requirements Document, Financial Analysis and Business Case
  • C. Low Level Design, Staging Plan, Operations Plan, Migration Plan
  • D. WLAN Site Readiness Assessment Report, voice over WLAN Assessment Report, Operations Readiness Assessment Report
  • E. Escalation Plan, Communication Plan, Staff Training Plan


Answer : C

Which of these service components are part of the plan phase?

  • A. WLAN Tuning assessment
  • B. WLAN site readiness assessment (RF survey)
  • C. Voice Over WLAN assessment
  • D. Migration plan development
  • E. WLAN location-based services assessment
  • F. WLAN performance and troubleshooting assessment


Answer : B,C,E

In plan phase, which tow tasks are associated with the conduct operational assessment activity? ( Choose two.)

  • A. Obtain and review operational procedures and policies
  • B. Document plan to remediate operational issues
  • C. Document systems, Processes, flow-through, tools, people, skill and best practices
  • D. Identify operations personnel and stakeholders for interviews
  • E. Conduct Operations personnel and stakeholders interviews


Answer : C,E

Informal basic training is conducted for helpdesk, admin, operations staff and end users.
Which two templates will help to accomplish this task? (Choose two.)

  • A. Network Ready for Use Template
  • B. WLAN Assessment Report
  • C. End User Training Template
  • D. Executive Interview Template
  • E. Staff training Template
  • F. Change Management Process Template


Answer : C,E

Which of these service components are part of the plan phase?

  • A. WLAN Tuning assessment
  • B. WLAN performance and troubleshooting assessment
  • C. WLAN location-based services assessment
  • D. Voice Over WLAN assessment
  • E. WLAN site readiness assessment (RF survey)
  • F. Migration plan development


Answer : C,D,E

Which one of these choices consists of a task or tasks included in the system migration service component of the implement phase?

  • A. Verify that escalation path is in place for difficulties with test cases
  • B. Define Requirements for Monitoring Service Level Measurements
  • C. Determine Project schedule, Develop Resource Plan, Establish Project Budget
  • D. Confirm Project milestones and cutover Roles and Responsibilities
  • E. Assess implementation readiness at each site, define timelines for Post-Implementation Testing, Execute Contingency Plans as required


Answer : E

Which document is a prerequisite to developing successfully migration plan?

  • A. Proof of Concept Report
  • B. High Level Design
  • C. Business Plan
  • D. Low Level Design
  • E. System Readiness Report


Answer : D

Which of these service components occur in the design phase?

  • A. WLAN wired Network Integration Assessment, WLAN location-based service assessment, security Architecture Assessment
  • B. Detailed Design Validation, Operation Plan, System Acceptance Test Plan Development
  • C. System Calibration, Project Planning Staff Training
  • D. High Level Design Development, proof of concept, Business Requirements Development


Answer : B