Cisco 650-575 - LCSAS Cisco Lifecycle Services Advanced Security Exam

Question #6 (Topic: Topic 0)
which service component in the design phase develops a plan that identifies the steps to
move from an existing system to a proposed system?
A. Business Plan Development B. Implementation Plan Development C. Business Requirements Document D. Staging Plan Development
Answer: B
Question #7 (Topic: Topic 0)
Which service component is part of the design phase?
A. Change Management B. Implementation Plan Development C. Site Readiness Assessment D. High-Level Design Development
Answer: B
Question #8 (Topic: Topic 0)
Which service component is in the security operate phase?
A. Change Management B. Operation Assessment C. Operations Design D. Security Technology Assessment
Answer: A
Question #9 (Topic: Topic 0)
Which design phase service component activity is part of the staging plan development?
A. Checking Hardware and Software Configuration B. Detailing Installation and Service Requirements in a Controlled Implementation Environment C. Planning an Escalation Notification Process D. Present Systems Acceptance Test Plan
Answer: B
Question #10 (Topic: Topic 0)
Which activity is included in the security business requirements development service
component in the prepare phase?
A. Conduct Executive Sponsor Interview B. Conduct Initial Interview C. Conduct Business Requirements Workshops D. Hold Partner and Cisco Systems Strategy Meeting
Answer: C