Question #1 (Topic: )
When powering on a Vblock System what is the correct power up sequence?
A. Switches, AMP, SAN, UCS chassis, and UCS blades
B. Switches, SAN, UCS chassis, UCS blades, and AMP
C. Switches, AMP, UCS chassis, UCS blades, and SAN
D. Switches, SAN, AMP, UCS chassis, and UCS blades
Answer: A
Question #2 (Topic: )
What are three primary site survey considerations? (Choose three.)
A. Site information
B. Technical resources
C. Customer power requirements
D. Data center physical audit
E. Disaster recovery plan
Answer: A,C,D
Question #3 (Topic: )
Which EMC software is required to initialize a Vblock System 200 storage array?
A. Unisphere Service Manager
B. Unisphere Server Utility
C. VNX Installation Assistant
D. Unisphere Client
Answer: C
Question #4 (Topic: )
Which EMC software is required to upgrade code on a Vblock System 200 storage array?
A. Unisphere Service Manager
B. Unisphere Server Utility
C. VNX Installation Assistant
D. Unisphere Client
Answer: A
Question #5 (Topic: )
Which two statements are correct about Vblock System Release Certification Matrix (RCM)
upgrades? (Choose two.)
upgrades? (Choose two.)
A. The RCM must be applied by VCE certified resources.
B. When upgrading to a new RCM, all components may not require an upgrade.
C. The most recent RCM version must be applied.
D. An addendum to the RCM may be issued to address a bug or software issue.
Answer: B,D