You must configure FCIP for a network 20 kilometers away and you do not want your fabrics to merge.
How would you configure the ports?

  • A. Configure an EX_Port on one end and a VEX_Port on the other end.
  • B. Configure a VE_Port at one end and a VEX_Port on the other end.
  • C. Configure an EX_Port at one end and a VE_Port on the other end.
  • D. Configure a VEX_Port on one end and a VEX_Port on the other end.


Answer : B

You need to implement an FCIP solution with one 10 Gbps FCIP tunnel.
Which Brocade product will provide the solution?

  • A. Brocade DCX 8510-4 with an FC6-10 blade
  • B. Brocade DCX with an FX8-24 blade
  • C. Brocade 7800 Extension Switch
  • D. Brocade DCX 8510-8 with an FCoE10-24 blade


Answer : B

You have connected two different backbone fabrics to the same edge fabric.
Which two statements are true? (Choose two.)

  • A. The edge fabric IDs must be different.
  • B. The backbone fabric IDs must be different.
  • C. The edge fabric IDs must be the same.
  • D. The backbone fabric IDs must be the same.


Answer : B,C

Your company acquires a new data center 100 km away. You decide to use an FCIP- shared infrastructure instead of dark fiber.
What are two advantages? (Choose two.)

  • A. FCIP has less protocol overhead.
  • B. FCIP leverages your investment in the IP infrastructure.
  • C. Less fiber is required.
  • D. FCIP uses jumbo frames.


Answer : B,C

You are configuring a 10 km long distance ISL between a Brocade DCX 8510 and a
Brocade 5300 with no additional license.
Which two configurations are needed? (Choose two.)

  • A. Configure the ISL ports at both ends for LE.
  • B. Configure the ISL ports at both ends for LD.
  • C. Configure the fill word to ARB on the ISL port of the 5300.
  • D. Configure the fill word to ARB on the ISL ports on both ends of the ISL.


Answer : A,C

You have allocated the correct number of buffers for your distance and speed on an extended distance link over dark fiber. However, you notice a latency issue being reported and the port is repeatedly starved for buffer credits.
What causes this to happen?

  • A. The front-end port de-bounce of 100 ms is too low.
  • B. The total allocated credits are divided between the VCs.
  • C. There is a large number of frames with small payload size.
  • D. There is a large number of frames with full or near full payload size.


Answer : C

You need to configure a long distance link that connects to a time-division multiplexer
(TDM).
Which two statements are true? (Choose two.)

  • A. You must disable QoS before configuring long distance.
  • B. You must disable R_RDY Mode before configuring long distance.
  • C. You must disable FC Fastwrite before configuring long distance.
  • D. You must disable Credit Recovery before configuring long distance.


Answer : A,D

You have configured ports 0-2 on your Brocade 6520 to a distance of 50 km at 16 Gbps.
As shown in the exhibit, port 2 was allocated more buffer credits than the other ports.


What is the reason for this happening?

  • A. Credit recovery is enabled.
  • B. Forward error correction is enabled.
  • C. Quality of Service is enabled.
  • D. Trunking is enabled.


Answer : C

Refer to the exhibit.


Referring to the exhibit, how many FCIP tunnels have been created?

  • A. 1
  • B. 2
  • C. 3
  • D. 4


Answer : B

Your application is using an average frame size of 1024 bytes across your long-distance links.
Which two actions will fully saturate the link? (Choose two.)

  • A. Set the port for LD and specify the distance.
  • B. Set the port for LD and specify the frame size.
  • C. Set the port for LS and specify the frame distance and size.
  • D. Set the port for LE and specify the distance and frame size.


Answer : B,C

You want to provision an additional FCIP tunnel between your data centers. You have FCP acceleration features enabled on the tunnels.
What must you do?

  • A. Configure IPsec.
  • B. Configure TI Zones.
  • C. Configure Adaptive Rate Limiting.
  • D. Configure the same committed rate on both circuits.


Answer : B

Refer to the exhibit.


ISLs have been created from VE12 to VE16, and VE13 to VE17.
Referring to the exhibit, how many FCIP circuits have been created?

  • A. 2
  • B. 3
  • C. 4
  • D. 6


Answer : C

You are configuring an FCIP tunnel with four circuits. Two of the circuits will be active and the other two will be in standby in case of failure. You want to ensure that there are always at least two active circuits in the event of a failure.
Which two steps will accomplish this task? (Choose two.)

  • A. Configure all the circuits as metric 1.
  • B. Configure two circuits as metric 1 and two circuits as metric 0.
  • C. Configure two failover groups consisting of a metric 1 and a metric 0 circuit per group.
  • D. Configure two failover groups consisting of two metric 1 circuits in one group and two metric 0 circuits in the second group.


Answer : B,C

A customer wants to connect an ISL between a Brocade DCX 8510 and a Brocade 5300 which are located 20 km apart at 8 Gbps through a DWDM.
Which two changes are required to the ports to enable error correction and communication between the devices? (Choose two.)
A. Enable ARB fill words on the Brocade 5300 E_Port.
B. Enable ARB fill words on the Brocade DCX 8510 E_Port.
C. Enable FEC on the DCX 8510 E_Port.
D. Enable FEC on the Brocade 5300 E_Port.



Answer : A,C Topic 7, Advanced Troubleshooting

Click the Exhibit button.


After troubleshooting a Brocade 7800, the VE_Port 16 is in offline state.
Referring to the exhibit, what should you disable?

  • A. Tperf
  • B. FC router
  • C. FCIP circuit
  • D. IPsec


Answer : A