Question #6 (Topic: Topic 1)
At the end of each Sprint the Scrumboard is _________.
A. Updated with new tasks and completed tasks.
B. Placed besides the new one to compare team velocities in Sprints.
C. Analyzed by the Scrum master to understand the project progress in that particular sprint.
D. Reset or wiped off.
Answer: C
Question #7 (Topic: Topic 1)
Emily has taken on the role of Scrum Master on a new project. Training the team is one of her major responsibilities. As Scrum Master, which aspects will Emily
need to address in this respect?
A) Gaps in technical knowledge in any of the team members.
B) Shortcomings in the Scrum Team's understanding of business value of features.
C) Increasing the team's capability to articulate their challenges to find solutions.
D) Lack of understanding of the Scrum processes and principles.
need to address in this respect?
A) Gaps in technical knowledge in any of the team members.
B) Shortcomings in the Scrum Team's understanding of business value of features.
C) Increasing the team's capability to articulate their challenges to find solutions.
D) Lack of understanding of the Scrum processes and principles.
A. B and C
B. A, B, and C
C. C only
D. C and D
Answer: D
Question #8 (Topic: Topic 1)
To enable the Product Owner to successfully deploy the product release as a part of the Ship Deliverables process, the Scrum Master should ensure that:
A. The Scrum Team creates Deliverables as agreed upon
B. The Release Plan and Prioritized Product Backlog are updated
C. The Scrum Team creates the Release Planning Schedule
D. The Scrum team Accepts/Rejects the deliverables during Demonstrate and Validate Sprint process
Answer: A
Question #9 (Topic: Topic 1)
Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have gathered together to create the Project Vision. They
are trying to determine and document the difference between current business capabilities and the final desired set of capabilities. Which one of the following
should they use to arrive at a conclusive decision?
are trying to determine and document the difference between current business capabilities and the final desired set of capabilities. Which one of the following
should they use to arrive at a conclusive decision?
A. Trial Project.
B. JAD Session.
C. Gap Analysis.
D. SWOT Analysis.
Answer: C
Question #10 (Topic: Topic 1)
Collaboration within a team is an important principle of Scrum. All of the following activities constitute collaboration EXCEPT:
A. The Scrum Team decides which User Stories are important and assigns which Sprint they should be worked on.
B. The Scrum Team discusses the best approach to creating deliverables during a Sprint.
C. A Scrum Team member is facing difficulties in one of his tasks and another team member pitches in to help him.
D. The Scrum Team interacts with the Product Owner to obtain clarification on User Stories.
Answer: A