Question #6 (Topic: Exam A)
Which two of the following apply during a project’s close out process? (Choose two.)
A. Communicate discrepancies to responsible parties.
B. Begin testing of installed infrastructure.
C. Evaluate the surroundings of the project and report back to the communications distribution professional of these findings.
D. Hire legal council for representation.
E. Create schedule for completion of punch list.
Answer: AE
Question #7 (Topic: Exam A)
Telecommunications cabling (e.g., voice, data, video, security, audio, control) can be damaged during the construction phases of rough-in, drywall installation, and during the siding of the exterior. For these reasons, telecommunications cabling shall be acceptance tested. Acceptance testing includes visual examination and verification of all cabling and qualification of copper cabling for data cabling or certification of copper or optical fiber cabling for data cabling. Verification testing is generally performed in which two of the following steps? (Choose two.)
A. Post the acceptance of the construction contract once the Project Manager has approved this phase
B. Prior to the installation of insulation and drywall
C. Prior to the installation of the cable tray system for spurs, points that would or could damage the cable infrastructure
D. During the trim-out stage of the cabling after painting
E. Post the implementation of the construction
Answer: BD
Question #8 (Topic: Exam A)
To properly size and provide accurate cost estimates for a communications distribution horizontal pathway that will include BAS system infrastructure, the designer should provide ________ for every BAS outlet or device based on total floor area.
A. 9.30 m2 (100 ft2)
B. 23.20 m2 (250 ft2)
C. 91.40 m2 (300 ft2)
D. 152.40 m2 (500 ft2)
Answer: B
Question #9 (Topic: Exam A)
Which of the following is the process of limiting fire and smoke using fire-resistive barriers?
A. Suppression
B. Prevention
C. Compartmentation
D. Detection
Answer: C
Question #10 (Topic: Exam A)
An ICT distribution designer is providing labeling for a data center room number 2A, located on the second floor having 10 rows of cabinets. Which of the following identifiers/labels would the designer attach to the bonding and grounding conductor between the first cabinet in the 6th row and the data center ground bar?
A. 2A/R601.1
B. 2A-SBB/R601.1
C. 2/R6
D. TEF1/R601.1
Answer: B