Question #6 (Topic: Exam A)
True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull system.
A. True B. False
Answer: A
Question #7 (Topic: Exam A)
What is the best chart to determine when a single item that has not been started will be finished?
A. WIP Aging chart. B. Throughput run chart. C. Cycle Time scatterplot. D. Cumulative Flow diagram (CFD).
Answer: C
Question #8 (Topic: Exam A)
Which of these is NOT a good description of Cycle Time?
A. The length of time a work item stays in one column. B. The time a work item takes from initial idea/concept to feedback returned from customers after a production release. C. The time a work item starts until when it finishes. D. The number of items that move into the delivery/end point per time period (e g., daily/weekly).
Answer: D
Question #9 (Topic: Exam A)
Which of these are typically included in the Definition of Workflow policies? (Choose six.)
A. The Increment. B. Work Item types. C. Service Level Expectations. D. Gantt chart. E. WIP limits. F. Visualization policies. G. Pull/prioritization policies. H. Definition of Done. I. Burndown chart.
Answer: BCEFGH
Question #10 (Topic: Exam A)
Which of the following are Kanban practices for Scrum?
A. Kaizen, remove delays, visualize policies, pull system. B. Visualizing flow, limiting WIP, actively managing the Work in Progress (WIP), inspecting & adapting the Workflow. C. T-shirt size estimation, service level expectations, limit WIP D. Class of service, cost of delay, visualize the Workflow, limit WIP, manage flow. E. Small batches, limit WIP, eliminate waste, Kaizen.
Answer: B