Question #1 (Topic: Exam A)
Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?
A. Increase the frequency of checkpoint reports B. Allow the team manager more flexibility to exceed cost tolerance C. Increase the frequency of event-driven controls D. Increase the frequency of escalations by the team manager
Answer: A
Question #2 (Topic: Exam A)
Which action contributes to achieving the ‘ensure continued business justification’ principle?
A. Adapting PRINCE2 Project Management to the scale and complexity of the project B. Assigning roles and responsibilities for the project team C. Establishing limits of authority on the project based on defined tolerances D. Ensuring that the project remains worthwhile throughout the lifecycle of the project
Answer: D
Question #3 (Topic: Exam A)
Which term is defined as the means by which an organization transitions from its current state to the target state?
A. Progress management B. Change control C. Change management D. Risk management
Answer: C
Question #4 (Topic: Exam A)
Which is a purpose of the communication management approach?
A. To describe the processes used to engage with stakeholders in identifying uncertainties B. To describe the techniques required to make the project product acceptable to stakeholders C. To describe the target organizational state and how the business will move to that new state D. To define how the project team intends to obtain responses from stakeholders
Answer: D
Question #5 (Topic: Exam A)
The project board needs to confirm that there is enough information to initiate the project.
What should the project beard review?
A. Project initiation documentation B. Project brief C. Benefits management approach D. Project plan
Answer: B