ITIL PR2F - PRINCE2 Foundation Exam Exam

Question #6 (Topic: Topic 1)
Which process provides the Project Board with the information it requires in order to
commit
resources to the project?
A. Managing Product Delivery B. Initiating a Project C. Controlling a Stage D. Directinga Project
Answer: B
Question #7 (Topic: Topic 1)
Which may be funded from a risk budget?
A. Corrections due to off-specifications B. Impact analysis of requests for change C. Implementation of a fallback plan D. Preparation of the Risk Management Strategy
Answer: C
Question #8 (Topic: Topic 1)
If an informal issue is defined as a problem or concern, where should it first be recorded?
A. Issue Register B. Risk Register C. Daily Log D. Exception Report
Answer: C
Question #9 (Topic: Topic 1)
Which is a task of product-based planning?
A. Design the plan B. Create the product flow diagram C. Analyze the risks D. Prepare the schedule
Answer: B
Question #10 (Topic: Topic 1)
Identify the missing words in the following sentence, The six aspects of project
performance to be managed are [?] costs, timescales and scope,
A. benefits, progress, risk, B. benefits, quality, risk, C. change, quality, progress, D. benefits, customers, quality,
Answer: B
Download Exam
Page: 2 / 60
Total 296 questions