Question #6 (Topic: Topic 1)
Which process provides the Project Board with the information it requires in order to
commit
resources to the project?
commit
resources to the project?
A. Managing Product Delivery
B. Initiating a Project
C. Controlling a Stage
D. Directinga Project
Answer: B
Question #7 (Topic: Topic 1)
Which may be funded from a risk budget?
A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. Implementation of a fallback plan
D. Preparation of the Risk Management Strategy
Answer: C
Question #8 (Topic: Topic 1)
If an informal issue is defined as a problem or concern, where should it first be recorded?
A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report
Answer: C
Question #9 (Topic: Topic 1)
Which is a task of product-based planning?
A. Design the plan
B. Create the product flow diagram
C. Analyze the risks
D. Prepare the schedule
Answer: B
Question #10 (Topic: Topic 1)
Identify the missing words in the following sentence, The six aspects of project
performance to be managed are [?] costs, timescales and scope,
performance to be managed are [?] costs, timescales and scope,
A. benefits, progress, risk,
B. benefits, quality, risk,
C. change, quality, progress,
D. benefits, customers, quality,
Answer: B