PMI PMI-200 - PMI Agile Certified Practitioner (PMI-ACP)® Exam
Page: 1 / 29
Total 145 questions
Question #1 (Topic: )
The ScrumMaster notices repeated friction between two team members in the Daily Scrum
meetings.The next step should be to:
meetings.The next step should be to:
A. Attempt to resolve the problem directly and immediately during a Daily Scrum meeting.
B. Schedule a meeting with them after a Daily Scrum meeting to explore and resolve the issue.
C. Ignore the friction because a self-organizing team must sort out team conflict issues.
D. Ask for new resources to replace them before the friction undermines the teams productivity.
Answer: B
Question #2 (Topic: )
The best approach to estimate the work on a project when using story points is to have:
A. Team members assign estimates by averaging Planning Poker cards.
B. The most senior team member prepare the estimates.
C. Two or three senior team members estimate and take the average of their times.
D. The team work together to agree on estimates in a group setting.
Answer: D
Question #3 (Topic: )
Team A is producing 61 points per iteration and Team B is producing 20 points per
iteration.Team A has more senior engineers.A manager demands that Team B match
Team As points in the next iteration.Based on this information, it is reasonable to tell the
manager that:
iteration.Team A has more senior engineers.A manager demands that Team B match
Team As points in the next iteration.Based on this information, it is reasonable to tell the
manager that:
A. it is impossible to compare two separate teams on points alone.
B. Team B’s points will match Team A if Team B gets more senior engineers.
C. Team B must have help self-organizing so their points match Team A.
D. Team B’s points will increase if the Product Owner becomes more involved.
Answer: A
Question #4 (Topic: )
When using Agile Earned Value Management (EVM), progress should be measured at
which level?
which level?
A. Task
B. Iteration
C. Product
D. Release
Answer: D
Question #5 (Topic: )
An Agile team best ensures product quality through:
A. The development team’s use of pair programming.
B. Quality assurance’s daily collaboration with the development team.
C. More frequent inspection after each iteration.
D. Feedback gathered during iteration retrospectives.
Answer: C