Question #6 (Topic: Exam A)
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
A. Apply the SDLC process. B. Establish a program. C. Consult the CCB. D. Use different frameworks.
Answer: B
Question #7 (Topic: Exam A)
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
A. Status report B. Project plan C. Change log D. Meeting minutes
Answer: D
Question #8 (Topic: Exam A)
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
A. Synchronous B. Informal C. Asynchronous D. Formal
Answer: A
Question #9 (Topic: Exam A)
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
A. Update the work breakdown structure. B. Review the backlog. C. Seek baseline approval. D. Establish the resource pool.
Answer: C
Question #10 (Topic: Exam A)
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
A. Trigger the contingency plan and communicate with the stakeholders. B. Work with the functional managers to create a work-around. C. Submit a change request to the change control board. D. Transfer the risk by hiring a new vendor who was successful on a previous project. E. Set up an escalation meeting with the sponsor.
Answer: A