Question #6 (Topic: )
Using Pegas implementation of Scrum, in which project phase would the Application
Profile document typically be initially created?
Profile document typically be initially created?
A. Enterprise Planning
B. Vision Definition
C. Project Initiation and Preparation
D. Scrum Implementation
Answer: C
Question #7 (Topic: )
When allocating resources for an Agile-based project, the project includes six system
architects. During the first three sprints, each system architect is allocated 50% to the
project, and each is estimated to be half as productive as a fully-trained system architect.
What is the number of architects you should enter in the Sizing tool for the first three
sprints?
architects. During the first three sprints, each system architect is allocated 50% to the
project, and each is estimated to be half as productive as a fully-trained system architect.
What is the number of architects you should enter in the Sizing tool for the first three
sprints?
A. 3 fully allocated system architects.
B. 3.5 fully trained system architects.
C. 1.5 fully allocated system architects.
D. 6 fully allocated system architects.
Answer: C
Question #8 (Topic: )
In a DCO session, which role is typically responsible for deriving test cases from the
requirements?
requirements?
A. System Architect
B. Moderator
C. Process Owner
D. QA Representative
E. Business Architect
Answer: E
Question #9 (Topic: )
When conducting DCO Sessions, a recommended best practice for managing parking lot
items is to ____________________.
items is to ____________________.
A. always assign the parking lot item to a system architect for follow-up
B. keep the list of open, unresolved items to between 5 and 10,
C. keep the list of open, unresolved items to no more than 5
D. always assign the parking lot item to a business stakeholder for follow-up
Answer: B
Question #10 (Topic: )
Using Scrum, whenshouldProject Sizing first be accomplished?
A. During Release Retrospective
B. During ProjectInitiation
C. During Release Implementation
D. During Vision Definition
E. During Enterprise Planning
Answer: B