Microsoft MB6-884 - Microsoft Dynamics AX 2012 Lean Manufacturing Exam

Question #6 (Topic: Topic 1)
You need to ensure that a new Kanban of the same type will be created whenever the
material handling unit associated with a Kanban is emptied.
Which replenishment strategy should you use?
A. Event B. Scheduled C. Fixed Quantity D. Stock Transfer
Answer: C
Question #7 (Topic: Topic 1)
Which Lean principle focuses on maximizing value-added content, minimizing waste, and
quickly adding value?
A. pull B. Flow C. Customer Value D. Perfection
Answer: C
Question #8 (Topic: Topic 1)
Which of the following functions are performed by production flows? (Each correct answer
presents a complete solution. Choose three.)
A. Outline the process and transfer activities of the Value Stream. B. Support the Kanban rules in defining the activities for a Kanban. C. Specify an activity-based framework for the planning and production processes. D. Provide a basic structure for planning, tracking, and processing orders based on pull signals from the customer. E. Set the pace of production based on the rate of demand from the customer.
Answer: A,B,C
Question #9 (Topic: Topic 1)
You are setting up the following three process activities in a production flow in Microsoft
Dynamics AX 2012:
The first process activity picks the bill of materials (BOM) components and outputs a
semi-finished product.
The second process activity picks the semi-finished product from the first activity and
outputs a different semi-finished product than the first activity.
The third process activity picks the semi-finished product from the second activity and
outputs a finished product.
How should you configure the first process activity?
A. To update the on-hand receipt and not receive the semi-finished product B. To update the on-hand receipt and receive the semi-finished product. C. To receive the semi-finished product and not update the on-hand receipt. D. To not receive the semi-finished product and not update the on-hand receipt.
Answer: C
Question #10 (Topic: Topic 1)
Which statement about a withdrawal Kanban in Microsoft Dynamics AX 2012 is true?
A. A withdrawal Kanban is planned. B. A withdrawal Kanban is visible on the Kanban schedule board. C. A withdrawal Kanban creates a process activity. D. A withdrawal Kanban moves the Kanban of an item between warehouses.
Answer: D