ISC ISSEP - ISSEP Information Systems Security Engineering Professional Exam
Page: 2 / 43
Total 213 questions
Question #6 (Topic: )
Part of your change management plan details what should happen in the change control
system for your project. Theresa, a junior project manager, asks what the configuration
management activities are for scope changes. You tell her that all of the following are valid
configuration management activities except for which one
system for your project. Theresa, a junior project manager, asks what the configuration
management activities are for scope changes. You tell her that all of the following are valid
configuration management activities except for which one
A. Configuration Item Costing
B. Configuration Identification
C. Configuration Verification and Auditing
D. Configuration Status Accounting
Answer: A
Question #7 (Topic: )
Which of the following professionals is responsible for starting the Certification &
Accreditation (C&A) process
Accreditation (C&A) process
A. Authorizing Official
B. Information system owner
C. Chief Information Officer (CIO)
D. Chief Risk Officer (CRO)
Answer: B
Question #8 (Topic: )
Which of the following security controls is a set of layered security services that address
communications and data security problems in the emerging Internet and intranet
application space
communications and data security problems in the emerging Internet and intranet
application space
A. Internet Protocol Security (IPSec)
B. Common data security architecture (CDSA)
C. File encryptors
D. Application program interface (API)
Answer: B
Question #9 (Topic: )
Which of the following protocols is used to establish a secure terminal to a remote network
device
device
A. WEP
B. SMTP
C. SSH
D. IPSec
Answer: C
Question #10 (Topic: )
Which of the following elements of Registration task 4 defines the system's external
interfaces as well as the purpose of each external interface, and the relationship between
the interface and the system
interfaces as well as the purpose of each external interface, and the relationship between
the interface and the system
A. System firmware
B. System software
C. System interface
D. System hardware
Answer: C