HP HP0-S45 - Delta - Integrating HP ProLiant Server Solutions Exam

Question #6 (Topic: )
Refer to trio exhibit.
[HP-HP0-S45-7.2/HP-HP0-S45-4_2.png]
A customer has an HP bi 460 Gen9 server in bay 9 that is using more network bandwidth
than expected. The server is installed m an HP C7000 BladeSystem Enclosure that has a
pair of HP Flexfabric 10Gb/24-Port modules m an Active/Active configuration managed by
HP OneView. The server integrator is investigating the bandwidth issue by viewing the
downlink bandwidth to bay 9 the current utilization is 0 Kb/s as shown.
Click the area that the integrator should select next to further investigate the Day 9
downlink bandwidth utilization.
Answer: [HP-HP0-S45-7.2/HP-HP0-S45-4_3.png]
Question #7 (Topic: )
Click on one of the HP recommended locations where an integrator should mount the iPDU
display on the cabinet.
[HP-HP0-S45-7.2/HP-HP0-S45-5_2.png]
Answer: [HP-HP0-S45-7.2/HP-HP0-S45-5_3.png]
Question #8 (Topic: )
A customer needs to implement HP OneView to manage a data center based on Gen9
servers running Windows OpenStack, and VMware.
Which other component can the integrator implement in this environment?
A. HP Helion CloudSystem for Windows and VMware deployment B. Insight Control server provisioning for OpenStack virtual machine deployment C. Microsoft System Center plugin for further integration D. HP Virtual Connect Enterprise Manager for profile management
Answer: A
Question #9 (Topic: )
What should the integrator use to back up HP OneVlew?
A. hypervisor provided Fault Tolerance on the HP OneView appliance virtual machine B. the HP OneView interface to generate and download a backup file C. HP Data Protector to back up the HP OneView appliance configuration D. hypervisor-provided capabilities to snapshot the HP OneView appliance virtual machine
Answer: B
Question #10 (Topic: )
Power was lost to an HP ProLiant DL380 Gen3 Server The system ROM is now corrupted
and the server can no longer boot.
What should the integrator do first to correct this problem?
A. Relocate the redundant ROM chip to the primary ROM chip. B. Replace the system board. C. Remove the system board battery for 60 seconds. D. Set the system maintenance switch positions S1,S5, and S6 to on.
Answer: D
Download Exam
Page: 2 / 12
Total 60 questions