Question #6 (Topic: Exam A)
What is a prerequisite for installing the TPM after replacing the system board in a PowerScale F900?
A. Verify the compatibility of the old TPM with the new system board.
B. Keep the old TPM installed on the new system board.
C. Ensure that a new TPM is available for installation.
Answer: C
Question #7 (Topic: Exam A)
Refer to the exhibit.

A platform engineer has connected power cables to a Dell PowerScale Gen6 node.
What does the status indicator indicate?

A platform engineer has connected power cables to a Dell PowerScale Gen6 node.
What does the status indicator indicate?
A. On and charging
B. Mismatch of voltage or component firmware
C. Standby and redundant
D. On and healthy
Answer: D
Question #8 (Topic: Exam A)
A platform engineer is building a new Dell PowerScale cluster. The Configuration Wizard prompts for a cluster name.
What is a consideration when entering the cluster name?
What is a consideration when entering the cluster name?
A. Must include a number and special character
B. Must include the Dell specific site ID
C. Must include the node 1 serial number
D. Must be unique to the network
Answer: D
Question #9 (Topic: Exam A)
Refer to the exhibit.

An engineer replaces the drive in C1. They run the isi devices drive list command and obtain the output that is shown.
What action must the engineer take?

An engineer replaces the drive in C1. They run the isi devices drive list command and obtain the output that is shown.
What action must the engineer take?
A. Run the isi devices drive add C1 command.
B. Run the isi devices drive format C1 command.
C. Update the firmware.
D. Contact Dell support.
Answer: D
Question #10 (Topic: Exam A)
A platform engineer must decide whether to reformat or reimage a Dell PowerScale node that is running the latest OneFS version.
What is a consideration?
What is a consideration?
A. Both processes wipe data and reinstall OneFS.
B. Reimaging requires updating any updates that were previously installed.
C. Reimaging reinstalls OneFS whereas reformatting does not.
D. Both processes reinstall the OneFS image.
Answer: C