Question #6 (Topic: Topic 1)
Working together with the test manager during test planning, which of the following
activities is NOT expected to be performed by the test analyst?
[K2] 1 credit
activities is NOT expected to be performed by the test analyst?
[K2] 1 credit
A. Review the test estimates of the test manager
B. Review the test plan for non-functional testing
C. Organize adequate test resources
D. Being involved in risk management sessions
Answer: C
Question #7 (Topic: Topic 1)
Which of the following statements is TRUE with respect to when the test analyst should
become involved during different lifecycle models?
[K2] 1 credit
become involved during different lifecycle models?
[K2] 1 credit
A. In a sequential V-model project the test analyst should start test analysis and design concurrently with coding
B. In Agile projects the test analyst should start test analysis and design concurrently with coding
C. In a sequential model project the test analyst should start test analysis and design concurrently with software design
D. In an embedded iterative model the test analyst should expect to be involved in the standard planning and design aspects
Answer: D
Question #8 (Topic: Topic 1)
Which of the following is a type of testing that someone in the role of a test analyst, working
with the test manager, should typically consider and plan for?
[K2] 1 credit
with the test manager, should typically consider and plan for?
[K2] 1 credit
A. Security testing
B. Reliability testing
C. Accessibility testing
D. Performance testing
Answer: C
Question #9 (Topic: Topic 1)
Which of the following is a typical work product that the Test Analyst would deliver as part
of the test closure activities?
[K2] 1 credit
A. A list of all deferred defects
B. A list of all rejected defect reports
C. A list of all defects found in production and fixed in this release
D. A list of all resolved defects
of the test closure activities?
[K2] 1 credit
A. A list of all deferred defects
B. A list of all rejected defect reports
C. A list of all defects found in production and fixed in this release
D. A list of all resolved defects
Answer: A
Topic 2, Test Management
Question #10 (Topic: Topic 2)
You are working as a tester on a project to develop a point-of-sales system for grocery
stores. Which of the following is a product risk that could be identified for such a system?
[K3] 2 credits
stores. Which of the following is a product risk that could be identified for such a system?
[K3] 2 credits
A. The arrival of a more reliable competing product on the market
B. Delivery of an incomplete test release to the first cycle of system test
C. An excessively high number of defect fixes fail during re-testing
D. Failure to accept allowed credit cards
Answer: D