IBM C2020-703 - IBM Cognos TM1 10.1 Administrator Exam
Page: 2 / 12
Total 57 questions
Question #6 (Topic: )
While troubleshooting a problem with a TurboIntegrator process, you must review log files
containing pertinent data.
Which two log files would you use? (Choose two.)
containing pertinent data.
Which two log files would you use? (Choose two.)
A. tm1web.log
B. tm1processerror.log
C. tm1server.log
D. tm1excelservice.log
Answer: B,C
Question #7 (Topic: )
You are asked to configure a TM1 Server for planning to minimize the chance of data loss
in case of a disaster with minimal impact on performance.
What should you do?
in case of a disaster with minimal impact on performance.
What should you do?
A. Set Logging to YES for all cubes.
B. Run CubeSaveData for all data entry cubes every 10 minutes
C. Run SaveDataAll every 10 minutes.
D. Set Logging to YES for only data entry cubes.
Answer: D
Question #8 (Topic: )
The TM1 Operations Console dynamically displays activity about the TM1 Server. Each
activity is shown as a thread in this display.
What are two examples of the information that is shown?
activity is shown as a thread in this display.
What are two examples of the information that is shown?
A. Thread feeder type (e.g., loaded or not loaded to memory)
B. Threadstate (e.g., Idle, Run, Commit, Rollback)
C. Thread type (e.g.. System, User, Chore)
D. Thread connectivity (e.g.. ODBC, ODBO, SAP)
Answer: B,C
Question #9 (Topic: )
A company has TM1 production servers scattered across the globe. The North American
server contains the base data that is used by all servers globally. The source data for the
North American TM1 Serverresides locally and is updated using an ODBC connection.
What is the optimal TM1 method for keeping the base data in the global TM1 servers
consistent with the base data in the North American TM1 Server?
server contains the base data that is used by all servers globally. The source data for the
North American TM1 Serverresides locally and is updated using an ODBC connection.
What is the optimal TM1 method for keeping the base data in the global TM1 servers
consistent with the base data in the North American TM1 Server?
A. Send copies of the TM1 log files from the North American server to the administrator of each global TM1 server and have them process it against their local TM1 Server.
B. Have a compressed copy of the North American production TM1 Server's data directory sent to the other global locations using FTP and restore this data onto each local TM1 Server.
C. Set up an ODBC connection to the North American production source data on each of the TM1 servers across the globe and run TurboIntegrator processes to update the global TM1 servers.
D. Set up a replication and synchronization nightly chore between the TM1 servers across the globe and the TM1 Server in North America.
Answer: D
Question #10 (Topic: )
You run a T1 process that imports data into a TM1 cube from a .csv file. The process
completes with a message "Process completed successfully", however when you check the
Target Cube, the cube shows all zeros.
Which log file would you review?
completes with a message "Process completed successfully", however when you check the
Target Cube, the cube shows all zeros.
Which log file would you review?
A. tm1s.log
B. tm1server.log
C. tm1web.log
D. tm1-log.properties
Answer: A