Question #6 (Topic: Topic 2)
Which sources of information can be used to capture data in a TSW ticket?
Note: There are 2 correct answers to this question.
A. Bill of material B. Load confirmation C. Inspector report D. Bill of lading
Answer: C,D
Question #7 (Topic: Topic 2)
Which process steps are performed during ticketing in TSW when actualizing standard
movement scenario3 (sales at destination) with incoterm DES?
A. Create delivery, create shipment, create discharge confirmation, update nomination B. Create goods movement, create shipment, create load confirmation, update nomination C. Create goods movement, create shipment, update nomination D. Create delivery, create shipment, create delivery confirmation, update nomination
Answer: D
Question #8 (Topic: Topic 2)
Standard posting groups are assigned to TSW movement scenarios. These posting groups
sometimes do not meet customer requirements and must be bypassed during ticketing.
To which relevance type do you assign the movement scenarios to bypass the standard
posting groups during ticketing?
A. Stock projection relevance B. Ticketing relevance C. Nomination relevance D. Document relevance
Answer: C
Question #9 (Topic: Topic 2)
The actualization of a TSW ticket has stopped with an error. How do you proceed?
A. Use the ticket reversal transaction and restart the ticketing process. B. Use the ticket deletion transaction to delete the ticket and create a new ticket with corrected values. C. Use the actualize ticket transaction after you have resolved the error outside ticketing. D. Use the ticket correction transaction to correct the erroneous values and rerun the ticket.
Answer: C
Question #10 (Topic: Topic 2)
Which process steps are performed during TSW ticketing when actualizing standard
movement scenario1 (purchase at origin) with incoterm FOB?
A. Create shipping notification, create shipment, create load confirmation, update nomination B. Create reservation, create shipping notification, create load confirmation, update nomination C. Create reservation, create shipment, create load confirmation, update nomination D. Create stock transfer order, create shipment, create load confirmation, update nomination
Answer: A