SAP C_ACTIVATE22 - SAP Certified Associate - SAP Activate Project Manager Exam

Question #6 (Topic: Topic 1. Transition Path "System Conversion" and "Selective Data Transition" )
What tool provides sizing estimations for the "System Conversion" transition path?
A. SAP Transformation Navigator B. Scope and Effort Analyzer C. SAP Best Practices Explorer D. SAP Readiness Check
Answer: D
Question #7 (Topic: Topic 1. Transition Path "System Conversion" and "Selective Data Transition" )
Which of the following are Selective Data Transition scenarios? (Choose three.)
A. Consolidation B. Migration of open items C. Migration of selected applications D. Migration of business units E. Migration of transactional data
Answer: BCD
Question #8 (Topic: Topic 2. Transition Path "Private and Public Cloud" )
Which of the following are cornerstones of SAP's security strategy? (Choose three.)
A. Secure Operations B. Secure Projects C. Secure Products D. Secure Company E. Secure Infrastructure
Answer: ACD
Question #9 (Topic: Topic 2. Transition Path "Private and Public Cloud" )
What transition scenarios are possible when adopting RISE with SAP? (Choose three.)
A. System Conversion B. Shell Conversion C. Lift and Shift D. Mix and Match E. New Implementation
Answer: ACE
Question #10 (Topic: Topic 2. Transition Path "Private and Public Cloud" )
Which system tenants are the first to be provisioned when implementing SAP S/4HANA Cloud, public edition?
A. SAP S/4HANA starter system B. SAP Cloud Identity Services C. SAP S/4HANA sandbox system D. Central Business Configuration System
Answer: A