Question #6 (Topic: Exam A)
During a design review, the administrator is asked to explain which underlying technology enables the NSX Edge to perform fast packet processing and achieve near line-rate performance for Virtual Network Functions (VNFs).
Which technology is leveraged in the NSX Edge for fast packet processing?
Which technology is leveraged in the NSX Edge for fast packet processing?
A. AMD Power Now
B. Intel Speed Step
C. Remote Direct Memory Access (RDMA)
D. Data Plane Development Kit (DPDK)
Answer: D
Question #7 (Topic: Exam A)
An administrator is tasked to capture traffic from a Virtual Machine (VM) running a critical application that is communicating with an unauthorized external endpoint.
How would an administrator capture the traffic?
How would an administrator capture the traffic?
A. Enable NetFlow sampling on the distributed port group.
B. Configure a distributed port mirroring session with the VM’s vNIC as the source.
C. Assign the VM to a promiscuous distributed port group.
D. Select the physical uplink on the virtual distributed switch as the target of the capture.
Answer: B
Question #8 (Topic: Exam A)
DRAG DROP
An administrator has been tasked explaining the benefits of Business Applications within VMware Cloud Foundation (VCF) Operations.
Drag and drop the three correct use cases from the Use Cases list on the left and place them into the Business Applications Use Cases list on the right in any order.
An administrator has been tasked explaining the benefits of Business Applications within VMware Cloud Foundation (VCF) Operations.
Drag and drop the three correct use cases from the Use Cases list on the left and place them into the Business Applications Use Cases list on the right in any order.
Answer:
Question #9 (Topic: Exam A)
An administrator is tasked with deploying a VMware Cloud Foundation (VCF) Workload Domain that meets the following requirements:
VSAN ESA as principal storage
RAID 6 with FTT=2
Support for Storage Traffic Separation
Cluster must support against entire rack failure
The administrator is provided the following hardware to perform the task:
Four ESX hosts, each host contains:
24 CPUs
96 GB memory
Two 25GbE network NICS
12 NVMe devices 4TB each, connected to a single SATA/SAS/NVMe Tri-mode controller
What five changes must the administrator make to the hardware before deploying the new Workload Domain? (Choose five.)
VSAN ESA as principal storage
RAID 6 with FTT=2
Support for Storage Traffic Separation
Cluster must support against entire rack failure
The administrator is provided the following hardware to perform the task:
Four ESX hosts, each host contains:
24 CPUs
96 GB memory
Two 25GbE network NICS
12 NVMe devices 4TB each, connected to a single SATA/SAS/NVMe Tri-mode controller
What five changes must the administrator make to the hardware before deploying the new Workload Domain? (Choose five.)
A. Increase the memory on each host to a minimum 128 GB.
B. Deploy the VSAN nodes across 4 server racks and enable fault domains in the vSphere client under “Hosts and Clusters”.
C. Increase the Tri-mode controller quantity on each host to two, with six NVMe devices connected to each.
D. Replace the network NICs on each host to a minimum of two 100 GbE network NICs.
E. Deploy the VSAN nodes across 6 server racks and enable fault domains in the vSphere client under “Hosts and Clusters”.
F. Increase the ESX host count to a minimum of six.
G. Increase the ESX host count to a minimum of seven.
H. Replace the Tri-mode controller on each host with a dedicated NVMe controller.
I. Increase the network NICs on each host to minimum of four 25 GbE network NICs.
Answer: AEGHI
Question #10 (Topic: Exam A)
A datacenter experienced a ransomware incident that caused extreme resource consumption for 48 hours before containment.
VMware Cloud Foundation (VCF) Operations capacity projections are now showing skewed Time Remaining values.
How would an administrator ensure accurate capacity planning going forward?
VMware Cloud Foundation (VCF) Operations capacity projections are now showing skewed Time Remaining values.
How would an administrator ensure accurate capacity planning going forward?
A. Use Data Exclusion to remove the time range from capacity calculations.
B. Reset all capacity calculations to start from today.
C. Change the risk level to Aggressive to compensate for the skewed values.
D. Wait for the anomalous data to age out naturally over time.
Answer: A