Which is a purpose of a Project Product Description?

  • A. Form part of the Work Package for the project product
  • B. Provide the initial project budget to be refined in the Business Case
  • C. Document the project mandate and gain approval for the project from the Project Board
  • D. Define the quality required of the project's product


Answer : D

What is defined as a temporary organization that is created for the purpose of delivering one or more business products?

  • A. Corporate or programme management
  • B. A project
  • C. A product breakdown structure
  • D. A user group


Answer : B

Where should an off-specification be recorded?

  • A. Risk Register
  • B. Issue Register
  • C. Work Package
  • D. Configuration Management Strategy


Answer : B

Which is an objective of the quality review technique?

  • A. To identify a product's quality criteria
  • B. To provide assurance that the project is being conducted properly
  • C. To assess that a product conforms to set criteria
  • D. To ensure that staff are properly trained in the quality methods


Answer : C

Which provides a single source of reference that may be used by people joining a project after it has been initiated so they can quickly and easily find out how the project is being managed?

  • A. Project Brief
  • B. Project Initiation Documentation
  • C. Project mandate
  • D. Project Product Description


Answer : B

Which statement about the Directing a Project process is FALSE?

  • A. Supports the PRINCE2 principle of manage by exception
  • B. Is triggered by a request to initiate a project
  • C. Covers the day-to-day activities of the Project Manager
  • D. Provides a mechanism for the Project Board to assure that there is continued business justification


Answer : C

Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

  • A. Change
  • B. Plans
  • C. Quality
  • D. Risk


Answer : D

Who should act as the communication channel between a project and corporate or programme management?

  • A. Project Board
  • B. Project Assurance
  • C. Project Manager
  • D. Project Support


Answer : A

Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,

  • A. Only 1 is true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Neither 1 or 2 are true


Answer : D

Which of the following is the Business Case used for during the Managing a Stage
Boundary process?

  • A. Enable the Project Board to decide whether or not to authorize the project
  • B. Justify the continuing viability of the project
  • C. Enable the Project Board to decide whether or not to authorize project closure
  • D. Justify the initiation of a project


Answer : B

Which role is responsible for the management of a risk assigned to it?

  • A. ProjectSupport
  • B. Risk owner
  • C. Risk actionee
  • D. Project Assurance


Answer : B

Which is NOT a purpose of the Organization theme?

  • A. Define a projectmanagement team structure
  • B. Define the level of tolerance for each level of the project management team
  • C. Define the Project Board's responsibility for directing the project
  • D. Define which role is accountable for the project's success


Answer : B

Which is a type of issue?

  • A. A lesson
  • B. A request for change
  • C. An Exception Report
  • D. A risk with an estimated high impact


Answer : B

How should the Team Manager report that tolerances are forecast to be exceeded?

  • A. Create an Exception Report
  • B. Create a Highlight Report
  • C. Raise an issue
  • D. Grant a concession


Answer : C

Which task is performed by the Change Authority?

  • A. Set a change budget
  • B. Approve or reject a request for change within approved limits
  • C. Refer changes that exceed budgetary limits to the Project Manager for approval
  • D. Update the configuration management system whena change is approved


Answer : B