__________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.
Answer : A
Explanation:
Rolling wave planning is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.
Which of the following activities is not part of Plan Risk Management?
Answer : A
Explanation:
Updating the risk register first happens in Identify Risks phase. Determining risk roles and responsibilities, Identifying risk categories and developing a risk management plan are part of Plan Risk Management.
PMI discusses procurement focusing on the ______ relationship.
Answer : A
Explanation:
PMI discusses procurement focusing on the buyer or seller relationship
Administrative closure is the process that ________.
Answer : A
Explanation:
Administrative closure: Closes all activities pertaining to a specific project
You are project manager of a project, which of the following is not your responsibility?
Answer : A
Explanation:
Senior management is responsible for quality in the organization
Project success can be achieved only if:
Answer : A
Explanation:
There is no project for the sake of spending money. There is a clear link between the project deliverables and the business strategy.
You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow's hierarchy of needs, what needs level he most likely is at?
Answer : A
Explanation:
as new to project he is most likely looking for acceptance and friendship. This comes under
Social need.
Which one of the following is not an output of contract closure?
Answer : D
Explanation:
All are output of contract closure: Close contracts,Contract file,Lessons learned documentation and Deliverable acceptance.
The intent of the risk management process group is to ________.
Answer : A
Explanation:
The risk management process group serves as the road map used to reduce its impact on the project.
ISO Stands for __________.
Answer : A
Explanation:
ISO Stands for International Organization for Standardization.
The project baseline is _______.
Answer : A
Explanation:
The project baseline: original plans plus the approved changes.
Which of the following is not a form a leadership power?
Answer : B
Explanation:
smoothing is a conflict resolution technique, the rest are forms of leadership power.
___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
Answer : A
Explanation:
Procurement Management is groups of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?
Answer : A
Explanation:
All the version you should keep in version control system.