An item in a production batch must be retested in 30 days to validate that it meets standards. You need to generate a report that informs you to retest the production batch in
30 days. What should you do?
Answer : B
You are distributing burden amounts from by-products based on a ratio of the by-product quantity to the formula size quantity. On the Formula lines form, which Burden value should you select on the formula version?
Answer : D
In Microsoft Dynamics AX 2012, how long are the results of a commodity pricing margin update calculation retained?
Answer : B
You need to set up a security group for existing Microsoft Dynamics SL users who use the
Accounts Payable module windows. Which of the following windows should you use?
Choose the 2 that apply.
Answer : A,B
You are applying a product template to an existing released product in Microsoft Dynamics
AX 2012.
Which of the following parameters must be identical between the product template the released product? (Each correct answer presents a complete solution. Choose three.)
Answer : A,D,E
Which type of rebate is typically processed by sending a check to the customer or by deducting the rebate amount from the customer's invoice in Microsoft Dynamics AX 2012?
Answer : D
Which of the following are prerequisites for installing the Management Reporter
Connector? Choose the 2 that apply.
Answer : C,D
A customer requests information about the physical and chemical properties of a product and the recommended precautions for handling storage and disposal of the product. Which of the following should you provide to the customer?
Answer : B
Which of the following statements about formula versions in Microsoft Dynamics AX 2012 are true? (Each correct answer presents a complete solution. Choose two.)
Answer : B,D
The formula for a finished good named FG-01 uses a raw material named RM-01. You currently have a supply of RM-01 in stock. The vendor informs you that only limited supplies of RM-01 will be available in the future. After you run out of the current supply of
RM-01you will substitute a raw material named RM-02 in the FG-01 formula. Which of the following options must you configure on a formula line to allow raw material substitutions in
Microsoft Dynamics AX 2012?
Answer : B
You plan to delete specific rebates by using the Purge rebate form.
Which of the following statuses must a rebate have so that it can be purged? (Each correct answer presents a complete solution. Choose two.)
Answer : B,C
You have a pricing template named PT-001, a pricing calculation named PC-01,a formula item named F-100.
The quantity margin template associated with PT-001 contains a line for item F-100, with the following variables specified for all customers:
-> Cost multiplier = X
-> Margin amount = Y
-> Margin percent = Z
Item F-100 uses a commodity ingredient that is defined on PC-01.
You run a pricing batch job for PC-01PT-001 with the new cost of item F-100 set to C.
How does Microsoft Dynamics AX 2012 calculate the new price of item F-100?
Answer : C
Which of the following characteristics apply only to a formula item and NOT to a bill of materials (BOM) item?
Answer : D
In Microsoft Dynamics AX 2012which of the following are valid rebate groups? (Each correct answer presents a complete solution. Choose two.)
Answer : A,D
A member of the Manager group is also a member of the AP group. The AP group has been given Insert rights to the Voucher and Adjustment Entry window. The Manager group has been given Delete rights to the Voucher and Adjustment Entry window. What is the highest level of rights that this member will have in the Voucher and Adjustment Entry window?
Answer : A